2026-09-06 03:17 PW As Needed Main Sewer Replacement No 10 completion date changed
schedule.end
2026-09-03 → 2027-09-02
2026-09-04 03:17 WD-2923 (formerly WD-2764): 24-inch Water Main Rehabilitation from University Mound Reservoir to 3rd St phase changed
phase
Design → Construction
2026-09-04 03:17 WD-2923 (formerly WD-2764): 24-inch Water Main Rehabilitation from University Mound Reservoir to 3rd St status changed
status
Started → Active
2026-09-04 03:17 Broad Street, Randolph Street, and San Jose Avenue Sewer Replacement start date changed
schedule.start
2027-05-29 → 2027-02-27
2026-09-04 03:17 Broad Street, Randolph Street, and San Jose Avenue Sewer Replacement completion date changed
schedule.end
2028-02-03 → 2027-11-04
2026-09-03 03:17 PW Oceanside Treatment Plant Construction completion date changed
schedule.end
2026-08-31 → 2026-11-30
2026-09-02 03:17 Slow Streets completion date changed
schedule.end
2026-12-31 → 2030-12-31
2026-09-01 03:17 South Sunset Clubhouse Renovation field removed
contact.email
alex.schuknecht@sfgov.org → —
2026-08-26 03:17 Bay Shore Blvd and Cesar Chavez Pavement Renovation completion date changed
schedule.end
2030-06-13 → 2029-01-21
2026-08-26 03:17 Bay Shore Blvd and Cesar Chavez Pavement Renovation start date changed
schedule.start
2029-03-30 → 2027-11-09
2026-08-21 03:17 PW Southeast Plant HVAC and Mechanical Upgrades completion date changed
schedule.end
2026-08-14 → 2026-12-31
2026-08-20 03:17 2021-008: 8-inch Ductile Iron Water Main Replacement on Moraga to Ortega, from 18th Ave to 15th Ave completion date changed
schedule.end
2027-04-30 → 2032-04-30
2026-08-20 03:17 2021-008: 8-inch Ductile Iron Water Main Replacement on Moraga to Ortega, from 18th Ave to 15th Ave start date changed
schedule.start
2025-04-01 → 2030-04-01
2026-08-20 03:17 SFMTA Parking Enforcement Headquarters completion date changed
schedule.end
2028-08-01 → 2028-10-17
2026-08-20 03:17 SFMTA Parking Enforcement Headquarters start date changed
schedule.start
2026-08-03 → 2026-10-19
2026-08-19 03:17 Various Locations Sewer Replacement No 25 completion date changed
schedule.end
2028-02-29 → 2028-03-31
2026-08-19 03:17 Various Locations Sewer Replacement No 25 start date changed
schedule.start
2027-01-25 → 2027-02-25
2026-08-16 03:17 PW Various Locations Curb Ramps No 18 start date changed
schedule.start
2026-05-04 → 2026-07-06
2026-08-16 03:17 PW Various Locations Curb Ramps No 18 phase changed
phase
Design → Construction
2026-08-16 03:17 Various Locations Sewer Replacement No 30 completion date changed
schedule.end
2028-05-07 → 2028-06-09
2026-08-16 03:17 Various Locations Sewer Replacement No 30 start date changed
schedule.start
2027-01-29 → 2027-03-03
2026-08-14 03:17 Various Locations Pavement Renovation No 68 completion date changed
schedule.end
2026-07-30 → 2026-09-30
2026-08-14 03:17 Various Locations Sewer Replacement No 28 completion date changed
schedule.end
2028-07-07 → 2028-08-21
2026-08-14 03:17 Various Locations Sewer Replacement No 28 start date changed
schedule.start
2027-01-15 → 2027-03-01
2026-08-14 03:17 Howard Streetscape Project completion date changed
schedule.end
2030-07-17 → 2031-04-17
2026-08-14 03:17 Howard Streetscape Project start date changed
schedule.start
2027-02-24 → 2027-11-25
2026-08-13 03:17 Western SOMA and Northern Mission Districts Sewer Replacement WW-719D completion date changed
schedule.end
2029-05-01 → 2029-03-30
2026-08-13 03:17 Western SOMA and Northern Mission Districts Sewer Replacement WW-719D start date changed
schedule.start
2027-07-29 → 2027-06-27
2026-08-11 03:17 PW Various Locations Sewer Replacement No 19 completion date changed
schedule.end
2027-12-31 → 2028-05-01
2026-08-11 03:17 PW Various Locations Sewer Replacement No 19 start date changed
schedule.start
2026-11-01 → 2027-03-03
2026-08-11 03:17 PW Main St Streetscape Drainage Improvements completion date changed
schedule.end
2026-07-22 → 2027-06-04
2026-08-11 03:17 PW Main St Streetscape Drainage Improvements start date changed
schedule.start
2025-01-18 → 2025-11-03
2026-08-11 03:17 PW Main St Streetscape Drainage Improvements phase changed
phase
Design → Construction
2026-08-11 03:17 Various Locations Sewer Replacement No 24 completion date changed
schedule.end
2028-01-25 → 2028-03-26
2026-08-11 03:17 Various Locations Sewer Replacement No 24 start date changed
schedule.start
2027-01-23 → 2027-03-25
2026-08-11 03:17 PW Various Locations Sewer Replacement No 21 completion date changed
schedule.end
2027-07-18 → 2027-10-02
2026-08-11 03:17 PW Various Locations Sewer Replacement No 21 start date changed
schedule.start
2026-07-18 → 2026-10-02
2026-08-11 03:17 Various Locations Sewer Replacement No 25 start date changed
schedule.start
2026-09-24 → 2027-01-25
2026-08-11 03:17 Seacliff No 2 Pump Station Refurb completion date changed
schedule.end
2027-01-20 → 2027-06-15
2026-08-11 03:17 Seacliff No 2 Pump Station Refurb start date changed
schedule.start
2024-11-14 → 2025-04-09
2026-08-11 03:17 Seacliff No 2 Pump Station Refurb phase changed
phase
Planning → Construction
2026-08-11 03:17 PW Geary BRT Phase 2 completion date changed
schedule.end
2028-06-30 → 2028-11-17
2026-08-11 03:17 PW Geary BRT Phase 2 start date changed
schedule.start
2026-06-03 → 2026-09-07
2026-08-11 03:17 Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements completion date changed
schedule.end
2028-07-13 → 2028-10-31
2026-08-11 03:17 Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements start date changed
schedule.start
2027-05-01 → 2027-08-02
2026-08-11 03:17 PW Various Locations Sewer Replacement No 20 completion date changed
schedule.end
2027-09-01 → 2027-11-06
2026-08-11 03:17 PW Various Locations Sewer Replacement No 20 start date changed
schedule.start
2026-09-01 → 2026-11-06
2026-08-11 03:17 Various Locations Pavement Renovation No 92 completion date changed
schedule.end
2027-05-19 → 2028-06-11
2026-08-11 03:17 Various Locations Pavement Renovation No 92 start date changed
schedule.start
2026-05-20 → 2027-03-29
2026-08-11 03:17 Various Locations Pavement Renovation No 92 phase changed
phase
Planning → Design
2026-08-11 03:17 Various Locations Pavement Renovation No 92 status changed
status
Pre-Planning → Active
2026-08-11 03:17 Various Locations Pavement Renovation No 81 and Sewer Replacement completion date changed
schedule.end
2027-04-12 → 2027-05-16
2026-08-11 03:17 Various Locations Pavement Renovation No 81 and Sewer Replacement phase changed
phase
Design → Construction
2026-08-11 03:17 Sunset Irrigation Recycled Water completion date changed
schedule.end
2028-09-25 → 2029-03-02
2026-08-11 03:17 Sunset Irrigation Recycled Water start date changed
schedule.start
2027-01-22 → 2027-06-29
2026-08-11 03:17 Western SOMA and Northern Mission Districts Sewer Replacement WW-719D completion date changed
schedule.end
2029-03-31 → 2029-05-01
2026-08-11 03:17 Western SOMA and Northern Mission Districts Sewer Replacement WW-719D start date changed
schedule.start
2027-06-28 → 2027-07-29
2026-08-11 03:17 Geary BRT Sewer Improvements Phase 2 completion date changed
schedule.end
2027-06-30 → 2027-08-25
2026-08-11 03:17 Geary BRT Sewer Improvements Phase 2 start date changed
schedule.start
2024-09-02 → 2024-10-28
2026-08-11 03:17 Geary BRT Sewer Improvements Phase 2 phase changed
phase
Design → Construction
2026-08-11 03:17 Mission, 8th, 9th, Howard and Natoma Brick Sewer Rehabilitation completion date changed
schedule.end
2026-11-06 → 2026-10-04
2026-08-11 03:17 Mission, 8th, 9th, Howard and Natoma Brick Sewer Rehabilitation phase changed
phase
Design → Construction
2026-08-11 03:17 Lakeview Summit Steps Project status changed
status
Active → Pre-Planning
2026-08-11 03:17 Various Locations Large Diameter Sewer Improvements No 1 completion date changed
schedule.end
2027-12-18 → 2028-04-01
2026-08-11 03:17 Various Locations Large Diameter Sewer Improvements No 1 start date changed
schedule.start
2026-11-19 → 2027-03-04
2026-08-11 03:17 Various Locations Pavement Renovation No 80 and Sewer Replacement completion date changed
schedule.end
2026-08-29 → 2027-03-29
2026-08-11 03:17 Various Locations Pavement Renovation No 80 and Sewer Replacement start date changed
schedule.start
2025-06-16 → 2026-02-23
2026-08-11 03:17 Various Locations Pavement Renovation No 80 and Sewer Replacement phase changed
phase
Planning → Construction
2026-08-11 03:17 Various Locations Pavement Renovation No 80 and Sewer Replacement status changed
status
Pre-Planning → Active
2026-08-08 03:17 Contract 35: Traffic Signal Modifications completion date changed
schedule.end
2027-11-30 → 2028-02-29
2026-08-08 03:17 Contract 35: Traffic Signal Modifications phase changed
phase
Design → Construction
2026-08-08 03:17 SFMTA Parking Enforcement Headquarters completion date changed
schedule.end
2027-10-14 → 2028-08-01
2026-08-08 03:17 SFMTA Parking Enforcement Headquarters start date changed
schedule.start
2025-10-15 → 2026-08-03
2026-08-07 03:17 EFWS Fort Mason Manifold Relocation phase changed
phase
Planning → Design
2026-08-07 03:17 Mission Street Safety Improvements Project completion date changed
schedule.end
2029-03-27 → 2030-06-30
2026-08-07 03:17 Mission Street Safety Improvements Project start date changed
schedule.start
2027-03-28 → 2028-06-30
2026-08-07 03:17 Western Addition Traffic Signal Upgrades Phase 2 completion date changed
schedule.end
2027-09-06 → 2028-10-27
2026-08-07 03:17 Western Addition Traffic Signal Upgrades Phase 2 start date changed
schedule.start
2026-09-11 → 2027-02-01
2026-08-05 03:17 Various Locations Pavement Renovation No 67B Sewer Replacement and Overhead Contact System Local Isolation completion date changed
schedule.end
2026-07-30 → 2026-08-31
2026-08-05 03:17 Chinatown Public Health Center phase changed
phase
Design → Construction
2026-07-31 03:18 Tenderloin Recreation Center Children’s Play Area Improvements field removed
contact.email
keri.ayers@sfgov.org → —
2026-07-31 03:17 PW Contract 35 Traffic Signal Upgrade completion date changed
schedule.end
2028-08-06 → 2028-01-27
2026-07-31 03:17 PW Contract 35 Traffic Signal Upgrade start date changed
schedule.start
2026-05-30 → 2026-06-29
2026-07-31 03:17 PW Contract 35 Traffic Signal Upgrade phase changed
phase
Design → Construction
2026-07-29 23:15 As Needed City-wide Pavement Preservation 6 (General As-Needed Contract G29) completion date changed
schedule.end
2028-01-28 → 2027-12-27
2026-07-29 23:15 As Needed City-wide Pavement Preservation 6 (General As-Needed Contract G29) start date changed
schedule.start
2025-05-04 → 2025-04-02
2026-07-29 23:15 As Needed City-wide Pavement Preservation 6 (General As-Needed Contract G29) phase changed
phase
Design → Construction
2026-07-29 23:15 Various Locations Pavement Renovation No 82 completion date changed
schedule.end
2027-09-14 → 2028-02-05
2026-07-29 23:15 Various Locations Pavement Renovation No 82 start date changed
schedule.start
2026-07-02 → 2026-11-23
2026-07-29 23:15 EFWS Fort Mason Manifold Relocation completion date changed
schedule.end
2030-09-16 → 2030-10-31
2026-07-29 23:15 EFWS Fort Mason Manifold Relocation start date changed
schedule.start
2028-09-15 → 2028-10-30
2026-07-29 23:15 Various Locations Pavement Renovation No 90 completion date changed
schedule.end
2027-05-30 → 2027-10-12
2026-07-29 23:15 Various Locations Pavement Renovation No 90 start date changed
schedule.start
2026-03-17 → 2026-07-20
2026-07-29 23:15 Various Locations Pavement Renovation No 90 phase changed
phase
Design → Construction
2026-07-29 23:15 PW Various Locations Sewer Replacement (JV VL PR No 90) phase changed
phase
Design → Construction
2026-07-29 23:15 PW Various Locations Sewer Replacement (JV VL PR No 82) completion date changed
schedule.end
2027-09-14 → 2028-02-05
2026-07-29 23:15 PW Various Locations Sewer Replacement (JV VL PR No 82) start date changed
schedule.start
2026-07-02 → 2026-11-23