Various Locations Pavement Renovation No 81 and Sewer Replacement
candidate project
Design
e4c54884-cf77-48e8-b168-04e15198eb18
This is a roadway paving and sewer replacement project managed by San Francisco Public Works (Streets & Highways division), spanning numerous street segments across the city, including stretches of Fell, Ellis, California, and Alhambra streets among roughly 71 locations. The project is currently in the design phase, with construction scheduled to run from January 2026 to April 2027. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Edmund.Lee@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Edmund.Lee@sfdpw.org” |
| contact.name | Edmund Lee |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Edmund Lee” |
| location.geometry | 71 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“71 published segment geometries” |
| location.street_limits | Alhambra St; Alhambra St from Pierce St to Avila St; Avery St; Buchanan St; California St from Laguna St to Buchanan St; Capra Way; Ellis St; Ellis St from Steiner St to Pierce St; Erkson Ct; Fell St; Fell St from Buchanan St to Webster St; Fell St from Fillmore St to Steiner St; Fell St from Franklin St to Gough St; Fell St from Gough St to Octavia St; Fell St from Laguna St to Buchanan St; Fell St from Octavia St to Laguna St; Fell St from Webster St to Fillmore St; Francisco St from Gough St to Octavia St; Gough St; Lyon St … |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Various Locations Pavement Renovation No 81 and Sewer Replacement |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Various Locations Pavement Renovation No 81 and Sewer Replacement” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2027-04-12 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2027-04-12T00:00:00.000” |
| schedule.start | 2026-01-28 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2026-01-28T00:00:00.000” |
| source.project_id | 8113 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 8113” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | This is a roadway paving and sewer replacement project managed by San Francisco Public Works (Streets & Highways... |
generated
llm:summarize · retrieved 2026-07-17
“generated from 12 resolved fields; input sha256-v2=6f8cdd7a8b738a77f1d795b6ec2be6ce4effdf6f552b28b3f883b4df24aaf4ca” |
Source records
| Public Works coordinated projects (DotMaps) | key 8113 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| summary | This is a roadway paving and sewer replacement project managed by San Francisco Public Works (Streets & Highways division), spanning numerous street segments across the city, including stretches of Fell, Ellis, California, and Alhambra streets among roughly 71 locations. The project is currently in the design phase, with construction scheduled to run from January 2026 to April 2027. No cost figures have been published. | generated | 2026-07-17 | live |
| location.geometry | 71 geometries | reported | 2026-07-17 | live |
| location.street_limits | Alhambra St; Alhambra St from Pierce St to Avila St; Avery St; Buchanan St; California St from Laguna St to Buchanan St; Capra Way; Ellis St; Ellis St from Steiner St to Pierce St; Erkson Ct; Fell St; Fell St from Buchanan St to Webster St; Fell St from Fillmore St to Steiner St; Fell St from Franklin St to Gough St; Fell St from Gough St to Octavia St; Fell St from Laguna St to Buchanan St; Fell St from Octavia St to Laguna St; Fell St from Webster St to Fillmore St; Francisco St from Gough St to Octavia St; Gough St; Lyon St … | derived | 2026-07-17 | live |
| schedule.end | 2027-04-12 | reported | 2026-07-17 | live |
| schedule.start | 2026-01-28 | reported | 2026-07-17 | live |
| source.project_id | 8113 | reported | 2026-07-17 | live |
| contact.email | Edmund.Lee@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Edmund Lee | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| name | Various Locations Pavement Renovation No 81 and Sewer Replacement | reported | 2026-07-17 | live |