PW Oceanside Treatment Plant Construction
PW Oceanside Treatment Plant Construction is a San Francisco Public Works (Bureau of Design and Construction, Architecture) project to plan, design, and build a new recycled water treatment plant, pump station, office space, and control rooms along the Great Highway between Sloat and Skyline Boulevards, at the Oceanside Wastewater Treatment Plant site. Originally slated for Golden Gate Park and later considered at the SF Zoo overflow parking area, the project is now located at Oceanside and is actively in construction, running from October 2017 to a scheduled completion in August 2026. The Public Utilities Commission's project budget is $158 million, with construction of the Recycled Water Facility and Chemical Building estimated at about $50.3 million.AI-generated
Updates (1)
What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.
-
detected Sep 3, 2026Recorded changeExpected completion changedExpected completion: 2026-08-31 → 2026-11-30
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW BDC - Architecture |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW BDC - Architecture” |
| contact.email | Reggie.Stump@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Reggie.Stump@sfdpw.org” |
| contact.name | Reggie Stump |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Reggie Stump” |
| description | The planning, design and construction of a new Treatment Plant, Pump Station, Office Space, and Control Rooms. The project site was originally located in the Golden Gate Park. In 2011, an alternative site at the SF Zoo overflow parking area is being considered by PUC. Currently-2013, the project site is located at the Ocenside Wasterwater Treatment Plant. PUC project budget $158M, CER construction cost for the Recycled Water Facility and the Chemical Building has been estimated at $50.26M and |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: The planning, design and construction of a new Treatment Plant, Pump Station, Office Space, and Control Rooms. The project site was originally...” |
| location.geometry | 1 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“1 published segment geometries” |
| location.street_limits | Great Hwy from Sloat Blvd to Skyline Blvd |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | PW Oceanside Treatment Plant Construction |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: PW Oceanside Treatment Plant Construction” |
| phase | Construction |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Construction” |
| project_type | Land |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Land” |
| schedule.end | 2026-11-30 |
reported
socrata:btxj-k9uh · retrieved 2026-09-03
“end_date: 2026-11-30T00:00:00.000” |
| schedule.start | 2017-10-18 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2017-10-18T00:00:00.000” |
| source.project_id | 25938 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 25938” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | PW Oceanside Treatment Plant Construction is a San Francisco Public Works (Bureau of Design and Construction,... |
generated
llm:summarize · retrieved 2026-07-18
“generated from 13 resolved fields; input sha256-v2=384661939883c74fa6f8e570354524301a67020e92ebd267b514f7fb245484f1” |
Changes
| 2026-09-03 | completion date changed | |
| 2026-08-27 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 25938 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| schedule.end | 2026-11-30 | reported | 2026-09-03 | live |
| location.geometry | 1 geometries | reported | 2026-08-27 | live |
| summary | PW Oceanside Treatment Plant Construction is a San Francisco Public Works (Bureau of Design and Construction, Architecture) project to plan, design, and build a new recycled water treatment plant, pump station, office space, and control rooms along the Great Highway between Sloat and Skyline Boulevards, at the Oceanside Wastewater Treatment Plant site. Originally slated for Golden Gate Park and later considered at the SF Zoo overflow parking area, the project is now located at Oceanside and is actively in construction, running from October 2017 to a scheduled completion in August 2026. The Public Utilities Commission's project budget is $158 million, with construction of the Recycled Water Facility and Chemical Building estimated at about $50.3 million. | generated | 2026-07-18 | live |
| location.geometry | 1 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | Great Hwy from Sloat Blvd to Skyline Blvd | derived | 2026-07-17 | live |
| schedule.end | 2026-08-31 | reported | 2026-07-17 | superseded |
| schedule.start | 2017-10-18 | reported | 2026-07-17 | live |
| source.project_id | 25938 | reported | 2026-07-17 | live |
| contact.email | Reggie.Stump@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Reggie Stump | reported | 2026-07-17 | live |
| agency.owner | SF DPW BDC - Architecture | reported | 2026-07-17 | live |
| project_type | Land | reported | 2026-07-17 | live |
| phase | Construction | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | The planning, design and construction of a new Treatment Plant, Pump Station, Office Space, and Control Rooms. The project site was originally located in the Golden Gate Park. In 2011, an alternative site at the SF Zoo overflow parking area is being considered by PUC. Currently-2013, the project site is located at the Ocenside Wasterwater Treatment Plant. PUC project budget $158M, CER construction cost for the Recycled Water Facility and the Chemical Building has been estimated at $50.26M and | reported | 2026-07-17 | live |
| name | PW Oceanside Treatment Plant Construction | reported | 2026-07-17 | live |