EFWS Fort Mason Manifold Relocation
candidate project
Design
4d15bcd9-a660-4ef0-981f-10c819e54a41
The EFWS Fort Mason Manifold Relocation is a San Francisco Public Works project to replace and relocate the Fort Mason fireboat manifold, part of the city's emergency firefighting water system, running along Bay Street and Laguna Street near the Marina. Owned by DPW's Mechanical division, the project is currently in the design phase, with construction scheduled to begin in October 2028 and finish in October 2030. No cost figures have been published.AI-generated
Updates (3)
What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.
-
detected Aug 7, 2026Recorded changePhase changedPhase: Planning → Design
-
detected Jul 29, 2026Recorded changeExpected completion changedExpected completion: 2030-09-16 → 2030-10-31
-
detected Jul 29, 2026Recorded changeStart changedStart: 2028-09-15 → 2028-10-30
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Mechanical |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Mechanical” |
| contact.email | Richard.Graham@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Richard.Graham@sfdpw.org” |
| contact.name | Richard Graham |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Richard Graham” |
| description | Replace and relocate Fort Mason Fireboat manifold |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: Replace and relocate Fort Mason Fireboat manifold” |
| location.geometry | 9 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“9 published segment geometries” |
| location.street_limits | Bay St; Bay St from Franklin St to Gough St; Bay St from Gough St to Octavia St; Bay St from Octavia St to Laguna St; Laguna St; Laguna St from Bay St to North Point St; Laguna St from North Point St to Marina Blvd |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | EFWS Fort Mason Manifold Relocation |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: EFWS Fort Mason Manifold Relocation” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-08-07
“project_phase: Design” |
| project_type | Water |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Water” |
| schedule.end | 2030-10-31 |
reported
socrata:btxj-k9uh · retrieved 2026-07-29
“end_date: 2030-10-31T00:00:00.000” |
| schedule.start | 2028-10-30 |
reported
socrata:btxj-k9uh · retrieved 2026-07-29
“start_date: 2028-10-30T00:00:00.000” |
| source.project_id | 8021 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 8021” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | The EFWS Fort Mason Manifold Relocation is a San Francisco Public Works project to replace and relocate the Fort... |
generated
llm:summarize · retrieved 2026-08-07
“generated from 13 resolved fields; input sha256-v2=f8b4fe8b3e13f98f645b465954c2a09737b4851f08386bfa1bf9588ddf9dc0cb” |
Changes
| 2026-08-27 | field changed immaterial | |
| 2026-08-07 | phase changed | |
| 2026-07-29 | completion date changed | |
| 2026-07-29 | start date changed |
Source records
| Public Works coordinated projects (DotMaps) | key 8021 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 9 geometries | reported | 2026-08-27 | live |
| summary | The EFWS Fort Mason Manifold Relocation is a San Francisco Public Works project to replace and relocate the Fort Mason fireboat manifold, part of the city's emergency firefighting water system, running along Bay Street and Laguna Street near the Marina. Owned by DPW's Mechanical division, the project is currently in the design phase, with construction scheduled to begin in October 2028 and finish in October 2030. No cost figures have been published. | generated | 2026-08-07 | live |
| phase | Design | reported | 2026-08-07 | live |
| summary | The EFWS Fort Mason Manifold Relocation is a planned water project by San Francisco Public Works (DPW IDC – Mechanical) to replace and relocate the Fort Mason fireboat manifold, part of the city's Emergency Firefighting Water System. The work spans Bay Street and Laguna Street in the northern waterfront area, near Fort Mason and the Marina. The project is currently in the planning phase and active, with construction scheduled to begin in October 2028 and finish in October 2030. No cost figures have been published. | generated | 2026-07-29 | superseded |
| schedule.end | 2030-10-31 | reported | 2026-07-29 | live |
| schedule.start | 2028-10-30 | reported | 2026-07-29 | live |
| summary | The EFWS Fort Mason Manifold Relocation is a water infrastructure project by SF Public Works to replace and relocate the Fort Mason Fireboat manifold, part of the city's Emergency Firefighting Water System. The work runs along Bay Street and Laguna Street in the Marina area. The project is currently in the planning phase, with construction scheduled to run from September 2028 to September 2030. No cost figures have been published. | generated | 2026-07-17 | superseded |
| location.geometry | 9 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | Bay St; Bay St from Franklin St to Gough St; Bay St from Gough St to Octavia St; Bay St from Octavia St to Laguna St; Laguna St; Laguna St from Bay St to North Point St; Laguna St from North Point St to Marina Blvd | derived | 2026-07-17 | live |
| schedule.end | 2030-09-16 | reported | 2026-07-17 | superseded |
| schedule.start | 2028-09-15 | reported | 2026-07-17 | superseded |
| source.project_id | 8021 | reported | 2026-07-17 | live |
| contact.email | Richard.Graham@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Richard Graham | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Mechanical | reported | 2026-07-17 | live |
| project_type | Water | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | superseded |
| status | Active | reported | 2026-07-17 | live |
| description | Replace and relocate Fort Mason Fireboat manifold | reported | 2026-07-17 | live |
| name | EFWS Fort Mason Manifold Relocation | reported | 2026-07-17 | live |