This is a street resurfacing project managed by San Francisco Public Works that will repave roadways, install ADA-compliant curb ramps, and rebuild portions of sub-sidewalk basements where needed to accommodate the new ramps. The work spans several downtown and North Beach streets, including Battery, Front, Montgomery, and Grant Avenue. The project is currently in the design phase, with construction scheduled to run from August 2027 to October 2028. No cost figures have been published.AI-generated
Updates (2)
What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.
-
detected Aug 11, 2026Recorded changeExpected completion changedExpected completion: 2028-07-13 → 2028-10-31
-
detected Aug 11, 2026Recorded changeStart changedStart: 2027-05-01 → 2027-08-02
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Anastastia.Haddad@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Anastastia.Haddad@sfdpw.org” |
| contact.name | Anastastia Haddad |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Anastastia Haddad” |
| description | Resurfacing at various locations, installing ADA curb ramps, and doing partial and/or full basement reconstruction to accomodate curb ramp construction. |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: Resurfacing at various locations, installing ADA curb ramps, and doing partial and/or full basement reconstruction to accomodate curb ramp construction.” |
| location.geometry | 10 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“10 published segment geometries” |
| location.street_limits | Battery St; Commercial St; Davis St; Front St; Grant Ave; Green St; Montgomery St; Sacramento St |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2028-10-31 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“end_date: 2028-10-31T00:00:00.000” |
| schedule.start | 2027-08-02 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“start_date: 2027-08-02T00:00:00.000” |
| source.project_id | 34631 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 34631” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | This is a street resurfacing project managed by San Francisco Public Works that will repave roadways, install... |
generated
llm:summarize · retrieved 2026-08-11
“generated from 13 resolved fields; input sha256-v2=b19a9244f1e837909724487a7006dcbc683f2faee4e19fed5c6697a75a96ffe2” |
Changes
| 2026-08-27 | field changed immaterial | |
| 2026-08-11 | completion date changed | |
| 2026-08-11 | start date changed |
Source records
| Public Works coordinated projects (DotMaps) | key 34631 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 10 geometries | reported | 2026-08-27 | live |
| summary | This is a street resurfacing project managed by San Francisco Public Works that will repave roadways, install ADA-compliant curb ramps, and rebuild portions of sub-sidewalk basements where needed to accommodate the new ramps. The work spans several downtown and North Beach streets, including Battery, Front, Montgomery, and Grant Avenue. The project is currently in the design phase, with construction scheduled to run from August 2027 to October 2028. No cost figures have been published. | generated | 2026-08-11 | live |
| schedule.end | 2028-10-31 | reported | 2026-08-11 | live |
| schedule.start | 2027-08-02 | reported | 2026-08-11 | live |
| summary | A San Francisco Public Works street improvement project in the northeastern part of the city, this effort will resurface roadways, install ADA-compliant curb ramps, and reconstruct portions of sub-sidewalk basements to accommodate the new ramps at various locations along streets including Battery, Front, and Montgomery. Owned by SF Public Works' Streets & Highways division, the project is currently in the design phase, with construction scheduled to run from May 2027 to July 2028. No cost figures have been published. | generated | 2026-07-18 | superseded |
| location.geometry | 10 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | Battery St; Commercial St; Davis St; Front St; Grant Ave; Green St; Montgomery St; Sacramento St | derived | 2026-07-17 | live |
| schedule.end | 2028-07-13 | reported | 2026-07-17 | superseded |
| schedule.start | 2027-05-01 | reported | 2026-07-17 | superseded |
| source.project_id | 34631 | reported | 2026-07-17 | live |
| contact.email | Anastastia.Haddad@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Anastastia Haddad | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | Resurfacing at various locations, installing ADA curb ramps, and doing partial and/or full basement reconstruction to accomodate curb ramp construction. | reported | 2026-07-17 | live |
| name | Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements | reported | 2026-07-17 | live |