Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements

candidate project Design 269b900d-071b-499f-b41d-c3ee6ebccc3b

This is a street resurfacing project managed by San Francisco Public Works that will repave roadways, install ADA-compliant curb ramps, and rebuild portions of sub-sidewalk basements where needed to accommodate the new ramps. The work spans several downtown and North Beach streets, including Battery, Front, Montgomery, and Grant Avenue. The project is currently in the design phase, with construction scheduled to run from August 2027 to October 2028. No cost figures have been published.AI-generated

Updates (2)

What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.

Current record

FieldValueProvenance
agency.owner SF DPW IDC - Streets & Highways reported socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways”
contact.email Anastastia.Haddad@sfdpw.org reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Anastastia.Haddad@sfdpw.org”
contact.name Anastastia Haddad reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Anastastia Haddad”
description Resurfacing at various locations, installing ADA curb ramps, and doing partial and/or full basement reconstruction to accomodate curb ramp construction. reported socrata:btxj-k9uh · retrieved 2026-07-17
“description: Resurfacing at various locations, installing ADA curb ramps, and doing partial and/or full basement reconstruction to accomodate curb ramp construction.”
location.geometry 10 geometries reported socrata:btxj-k9uh · retrieved 2026-08-27
“10 published segment geometries”
location.street_limits Battery St; Commercial St; Davis St; Front St; Grant Ave; Green St; Montgomery St; Sacramento St derived socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields”
name Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements reported socrata:btxj-k9uh · retrieved 2026-07-17
“name: Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements”
phase Design reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design”
project_type Roadway reported socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway”
schedule.end 2028-10-31 reported socrata:btxj-k9uh · retrieved 2026-08-11
“end_date: 2028-10-31T00:00:00.000”
schedule.start 2027-08-02 reported socrata:btxj-k9uh · retrieved 2026-08-11
“start_date: 2027-08-02T00:00:00.000”
source.project_id 34631 reported socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 34631”
status Active reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active”
summary This is a street resurfacing project managed by San Francisco Public Works that will repave roadways, install... generated llm:summarize · retrieved 2026-08-11
“generated from 13 resolved fields; input sha256-v2=b19a9244f1e837909724487a7006dcbc683f2faee4e19fed5c6697a75a96ffe2”

Changes

2026-08-27 field changed immaterial {'type': 'GeometryCollection', 'geometries': [{'type': 'Point', 'coordinates': [-122.3977962567628, 37.79443400661903]}, {'type': 'Point', 'coordinates': [-122.39897025417353, 37.79428441533399]}, {'type': 'Point', 'coordinates': [-122.4001487789528, 37.794134234776905]}, {'type': 'Point', 'coordinates': [-122.40401611419338, 37.79364630928349]}, {'type': 'Point', 'coordinates': [-122.40295736072363, 37.793779857610694]}, {'type': 'Point', 'coordinates': [-122.40471058225177, 37.79402138046282]}, {'type': 'Point', 'coordinates': [-122.40647555105532, 37.795144464704066]}, {'type': 'Point', 'coordinates': [-122.40665235217716, 37.79602475022813]}, {'type': 'Point', 'coordinates': [-122.40682767782573, 37.796901905921096]}, {'type': 'Point', 'coordinates': [-122.41064427351984, 37.79930285367294]}]}{'type': 'GeometryCollection', 'geometries': [{'type': 'Point', 'coordinates': [-122.39779626, 37.79443401]}, {'type': 'Point', 'coordinates': [-122.39897025, 37.79428442]}, {'type': 'Point', 'coordinates': [-122.40014878, 37.79413423]}, {'type': 'Point', 'coordinates': [-122.40401611, 37.79364631]}, {'type': 'Point', 'coordinates': [-122.40295736, 37.79377986]}, {'type': 'Point', 'coordinates': [-122.40471058, 37.79402138]}, {'type': 'Point', 'coordinates': [-122.40647555, 37.79514446]}, {'type': 'Point', 'coordinates': [-122.40665235, 37.79602475]}, {'type': 'Point', 'coordinates': [-122.40682768, 37.79690191]}, {'type': 'Point', 'coordinates': [-122.41064427, 37.79930285]}]}
2026-08-11 completion date changed 2028-07-132028-10-31
2026-08-11 start date changed 2027-05-012027-08-02

Source records

Public Works coordinated projects (DotMaps) key 34631 primary · rule:dotmaps-group-by-dotmapsid dataset page ↗ · this record’s data ↗

Assertion history (latest 100, including superseded)

PredicateValueClassRecordedState
location.geometry 10 geometries reported 2026-08-27 live
summary This is a street resurfacing project managed by San Francisco Public Works that will repave roadways, install ADA-compliant curb ramps, and rebuild portions of sub-sidewalk basements where needed to accommodate the new ramps. The work spans several downtown and North Beach streets, including Battery, Front, Montgomery, and Grant Avenue. The project is currently in the design phase, with construction scheduled to run from August 2027 to October 2028. No cost figures have been published. generated 2026-08-11 live
schedule.end 2028-10-31 reported 2026-08-11 live
schedule.start 2027-08-02 reported 2026-08-11 live
summary A San Francisco Public Works street improvement project in the northeastern part of the city, this effort will resurface roadways, install ADA-compliant curb ramps, and reconstruct portions of sub-sidewalk basements to accommodate the new ramps at various locations along streets including Battery, Front, and Montgomery. Owned by SF Public Works' Streets & Highways division, the project is currently in the design phase, with construction scheduled to run from May 2027 to July 2028. No cost figures have been published. generated 2026-07-18 superseded
location.geometry 10 geometries reported 2026-07-17 superseded
location.street_limits Battery St; Commercial St; Davis St; Front St; Grant Ave; Green St; Montgomery St; Sacramento St derived 2026-07-17 live
schedule.end 2028-07-13 reported 2026-07-17 superseded
schedule.start 2027-05-01 reported 2026-07-17 superseded
source.project_id 34631 reported 2026-07-17 live
contact.email Anastastia.Haddad@sfdpw.org reported 2026-07-17 live
contact.name Anastastia Haddad reported 2026-07-17 live
agency.owner SF DPW IDC - Streets & Highways reported 2026-07-17 live
project_type Roadway reported 2026-07-17 live
phase Design reported 2026-07-17 live
status Active reported 2026-07-17 live
description Resurfacing at various locations, installing ADA curb ramps, and doing partial and/or full basement reconstruction to accomodate curb ramp construction. reported 2026-07-17 live
name Various Locations No 71B Paving, Curb Ramps and Sub-sidewalk Basements reported 2026-07-17 live