PW Various Locations Curb Ramps No 18
candidate project
Construction
eb15dcf2-78fc-40d9-a448-05880c1fe1cf
The PW Various Locations Curb Ramps No 18 is a San Francisco Public Works project to plan and design new curb ramps at several locations across the city, including sites along 8th Street, Alemany Boulevard, and Octavia Street, with construction funded under Prop K. Owned by Public Works' Streets & Highways division, the project is active and has moved into its construction phase, scheduled to run from July 2026 through May 2027.AI-generated
Updates (2)
What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.
-
detected Aug 16, 2026Recorded changePhase changedPhase: Design → Construction
-
detected Aug 16, 2026Recorded changeStart changedStart: 2026-05-04 → 2026-07-06
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Anastastia.Haddad@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Anastastia.Haddad@sfdpw.org” |
| contact.name | Anastastia Haddad |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Anastastia Haddad” |
| description | This project will provide planning and design for San Francisco Public Works Curb Ramp Program. After design the Construction to be done under Prop K funding. |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: This project will provide planning and design for San Francisco Public Works Curb Ramp Program. After design the Construction to be done under...” |
| location.geometry | 7 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“7 published segment geometries” |
| location.street_limits | 08th St; Alemany Blvd from Industrial St On Ramp to Hwy 101 N On Ramp \ San Bruno Av Off Ramp; Ashbury St; Bay St; Brush Pl; Egbert Ave; Octavia St |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | PW Various Locations Curb Ramps No 18 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: PW Various Locations Curb Ramps No 18” |
| phase | Construction |
reported
socrata:btxj-k9uh · retrieved 2026-08-16
“project_phase: Construction” |
| project_type | Sanitary Sewer |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“facility_type: Sanitary Sewer” |
| schedule.end | 2027-05-30 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2027-05-30T00:00:00.000” |
| schedule.start | 2026-07-06 |
reported
socrata:btxj-k9uh · retrieved 2026-08-16
“start_date: 2026-07-06T00:00:00.000” |
| source.project_id | 31417 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 31417” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | The PW Various Locations Curb Ramps No 18 is a San Francisco Public Works project to plan and design new curb ramps... |
generated
llm:summarize · retrieved 2026-08-16
“generated from 13 resolved fields; input sha256-v2=9f29a6d399e30e53dff5b17edca0b62e77448bd0da25d792e75a62454ab90da0” |
Changes
| 2026-08-27 | field changed immaterial | |
| 2026-08-16 | start date changed | |
| 2026-08-16 | phase changed | |
| 2026-08-11 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 31417 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 7 geometries | reported | 2026-08-27 | live |
| summary | The PW Various Locations Curb Ramps No 18 is a San Francisco Public Works project to plan and design new curb ramps at several locations across the city, including sites along 8th Street, Alemany Boulevard, and Octavia Street, with construction funded under Prop K. Owned by Public Works' Streets & Highways division, the project is active and has moved into its construction phase, scheduled to run from July 2026 through May 2027. | generated | 2026-08-16 | live |
| schedule.start | 2026-07-06 | reported | 2026-08-16 | live |
| phase | Construction | reported | 2026-08-16 | live |
| summary | San Francisco Public Works is planning and designing a new round of curb ramps at various locations across the city, including sites along 8th Street, Alemany Boulevard, Ashbury Street and several other streets. Managed by the department's Streets & Highways division, the project is currently in the design phase, with work scheduled to run from May 2026 to May 2027; construction is to follow under Prop K funding. No cost figures have been published. | generated | 2026-08-11 | superseded |
| project_type | Sanitary Sewer | reported | 2026-08-11 | live |
| summary | The PW Various Locations Curb Ramps No 18 is a San Francisco Public Works project that will provide planning and design for the city's Curb Ramp Program, with construction to follow later under Prop K funding. The work spans several locations across the city, including sites along 8th Street, Alemany Boulevard, Bay Street, and Octavia Street. Owned by SF Public Works' Streets & Highways division, the project is currently active and in the design phase, scheduled to run from May 2026 to May 2027. No cost figures have been published. | generated | 2026-07-18 | superseded |
| location.geometry | 7 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | 08th St; Alemany Blvd from Industrial St On Ramp to Hwy 101 N On Ramp \ San Bruno Av Off Ramp; Ashbury St; Bay St; Brush Pl; Egbert Ave; Octavia St | derived | 2026-07-17 | live |
| schedule.end | 2027-05-30 | reported | 2026-07-17 | live |
| schedule.start | 2026-05-04 | reported | 2026-07-17 | superseded |
| source.project_id | 31417 | reported | 2026-07-17 | live |
| contact.email | Anastastia.Haddad@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Anastastia Haddad | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-07-17 | live |
| project_type | Sanitary Sewer, Roadway | reported | 2026-07-17 | superseded |
| phase | Design | reported | 2026-07-17 | superseded |
| status | Active | reported | 2026-07-17 | live |
| description | This project will provide planning and design for San Francisco Public Works Curb Ramp Program. After design the Construction to be done under Prop K funding. | reported | 2026-07-17 | live |
| name | PW Various Locations Curb Ramps No 18 | reported | 2026-07-17 | live |