SFMTA Parking Enforcement Headquarters
The SFMTA Parking Enforcement Headquarters is a planned project to convert the old Animal Care and Control building at 1200 15th Street in San Francisco's Mission District into a new headquarters for the SFMTA's Parking and Traffic Enforcement Division. Managed by San Francisco Public Works, the project would seismically retrofit the existing two-story concrete building, replace its mechanical, electrical, plumbing, and fire protection systems to meet current code, and add a new solar photovoltaic panel system. The project is currently in the design phase, with construction scheduled from August 2026 through August 2028, roughly ten months later than originally planned. No cost figures have been published.AI-generated
Updates (4)
What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.
-
detected Aug 20, 2026Recorded changeExpected completion changedExpected completion: 2028-08-01 → 2028-10-17
-
detected Aug 20, 2026Recorded changeStart changedStart: 2026-08-03 → 2026-10-19
-
detected Aug 8, 2026Recorded changeExpected completion changedExpected completion: 2027-10-14 → 2028-08-01
-
detected Aug 8, 2026Recorded changeStart changedStart: 2025-10-15 → 2026-08-03
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW BDC - Building Project Management |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW BDC - Building Project Management” |
| contact.email | Michael.Rossetto@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Michael.Rossetto@sfdpw.org” |
| contact.name | Michael Rossetto |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Michael Rossetto” |
| description | The Proposed Project Scope: The proposed project scope is to create a new headquarters for SFMTA’s Parking and Traffic Enforcement Division at 1200 - 15th Street in the old Animal Care and Control (ACC) building after its rehabilitation. The existing two-story concrete building will be seismically retrofitted and building systems such as Mechanical, Electrical, Plumbing and Fire Protection will be replaced to meet the current building code. In addition, a new solar photovoltaic panel system will |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: The Proposed Project Scope: The proposed project scope is to create a new headquarters for SFMTA’s Parking and Traffic Enforcement Division at...” |
| location.geometry | 6 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“6 published segment geometries” |
| location.street_limits | 15th St; 15th St from Alabama St to Treat Ave; Alabama St from Treat Ave to 15th St; Harrison St from Alameda St to 15th St |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | SFMTA Parking Enforcement Headquarters |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: SFMTA Parking Enforcement Headquarters” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Sanitary Sewer |
reported
socrata:btxj-k9uh · retrieved 2026-08-08
“facility_type: Sanitary Sewer” |
| schedule.end | 2028-10-17 |
reported
socrata:btxj-k9uh · retrieved 2026-08-20
“end_date: 2028-10-17T00:00:00.000” |
| schedule.start | 2026-10-19 |
reported
socrata:btxj-k9uh · retrieved 2026-08-20
“start_date: 2026-10-19T00:00:00.000” |
| source.project_id | 22962 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 22962” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | The SFMTA Parking Enforcement Headquarters is a planned project to convert the old Animal Care and Control building... |
generated
llm:summarize · retrieved 2026-08-08
“generated from 13 resolved fields; input sha256-v2=4ea4a6c8f04fb9d9b84cc085614209ec68dfc6381a3aab148477855f6ed5052c” |
Changes
| 2026-08-27 | field changed immaterial | |
| 2026-08-20 | completion date changed | |
| 2026-08-20 | start date changed | |
| 2026-08-08 | completion date changed | |
| 2026-08-08 | start date changed | |
| 2026-08-08 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 22962 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 6 geometries | reported | 2026-08-27 | live |
| schedule.end | 2028-10-17 | reported | 2026-08-20 | live |
| schedule.start | 2026-10-19 | reported | 2026-08-20 | live |
| summary | The SFMTA Parking Enforcement Headquarters is a planned project to convert the old Animal Care and Control building at 1200 15th Street in San Francisco's Mission District into a new headquarters for the SFMTA's Parking and Traffic Enforcement Division. Managed by San Francisco Public Works, the project would seismically retrofit the existing two-story concrete building, replace its mechanical, electrical, plumbing, and fire protection systems to meet current code, and add a new solar photovoltaic panel system. The project is currently in the design phase, with construction scheduled from August 2026 through August 2028, roughly ten months later than originally planned. No cost figures have been published. | generated | 2026-08-08 | live |
| schedule.end | 2028-08-01 | reported | 2026-08-08 | superseded |
| schedule.start | 2026-08-03 | reported | 2026-08-08 | superseded |
| project_type | Sanitary Sewer | reported | 2026-08-08 | live |
| summary | The SFMTA Parking Enforcement Headquarters is a planned City project to convert the former Animal Care and Control building at 1200 15th Street, in San Francisco's Mission District, into a new headquarters for SFMTA's Parking and Traffic Enforcement Division. Managed by San Francisco Public Works, the project would seismically retrofit the existing two-story concrete building, replace its mechanical, electrical, plumbing, and fire-protection systems to meet current code, and add a new rooftop solar panel system. The project is currently in the design phase, with construction-related work scheduled to run from October 2025 through October 2027. No cost figures have been published. | generated | 2026-07-18 | superseded |
| location.geometry | 6 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | 15th St; 15th St from Alabama St to Treat Ave; Alabama St from Treat Ave to 15th St; Harrison St from Alameda St to 15th St | derived | 2026-07-17 | live |
| schedule.end | 2027-10-14 | reported | 2026-07-17 | superseded |
| schedule.start | 2025-10-15 | reported | 2026-07-17 | superseded |
| source.project_id | 22962 | reported | 2026-07-17 | live |
| contact.email | Michael.Rossetto@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Michael Rossetto | reported | 2026-07-17 | live |
| agency.owner | SF DPW BDC - Building Project Management | reported | 2026-07-17 | live |
| project_type | Sanitary Sewer, Land, Roadway | reported | 2026-07-17 | superseded |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | The Proposed Project Scope: The proposed project scope is to create a new headquarters for SFMTA’s Parking and Traffic Enforcement Division at 1200 - 15th Street in the old Animal Care and Control (ACC) building after its rehabilitation. The existing two-story concrete building will be seismically retrofitted and building systems such as Mechanical, Electrical, Plumbing and Fire Protection will be replaced to meet the current building code. In addition, a new solar photovoltaic panel system will | reported | 2026-07-17 | live |
| name | SFMTA Parking Enforcement Headquarters | reported | 2026-07-17 | live |