The SFMTA Parking Enforcement Headquarters is a planned project to convert the old Animal Care and Control building at 1200 15th Street in San Francisco's Mission District into a new headquarters for the SFMTA's Parking and Traffic Enforcement Division. Managed by San Francisco Public Works, the project would seismically retrofit the existing two-story concrete building, replace its mechanical, electrical, plumbing, and fire protection systems to meet current code, and add a new solar photovoltaic panel system. The project is currently in the design phase, with construction scheduled from August 2026 through August 2028, roughly ten months later than originally planned. No cost figures have been published.AI-generated

Updates (4)

What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.

Current record

FieldValueProvenance
agency.owner SF DPW BDC - Building Project Management reported socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW BDC - Building Project Management”
contact.email Michael.Rossetto@sfdpw.org reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Michael.Rossetto@sfdpw.org”
contact.name Michael Rossetto reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Michael Rossetto”
description The Proposed Project Scope: The proposed project scope is to create a new headquarters for SFMTA’s Parking and Traffic Enforcement Division at 1200 - 15th Street in the old Animal Care and Control (ACC) building after its rehabilitation. The existing two-story concrete building will be seismically retrofitted and building systems such as Mechanical, Electrical, Plumbing and Fire Protection will be replaced to meet the current building code. In addition, a new solar photovoltaic panel system will reported socrata:btxj-k9uh · retrieved 2026-07-17
“description: The Proposed Project Scope: The proposed project scope is to create a new headquarters for SFMTA’s Parking and Traffic Enforcement Division at...”
location.geometry 6 geometries reported socrata:btxj-k9uh · retrieved 2026-08-27
“6 published segment geometries”
location.street_limits 15th St; 15th St from Alabama St to Treat Ave; Alabama St from Treat Ave to 15th St; Harrison St from Alameda St to 15th St derived socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields”
name SFMTA Parking Enforcement Headquarters reported socrata:btxj-k9uh · retrieved 2026-07-17
“name: SFMTA Parking Enforcement Headquarters”
phase Design reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design”
project_type Sanitary Sewer reported socrata:btxj-k9uh · retrieved 2026-08-08
“facility_type: Sanitary Sewer”
schedule.end 2028-10-17 reported socrata:btxj-k9uh · retrieved 2026-08-20
“end_date: 2028-10-17T00:00:00.000”
schedule.start 2026-10-19 reported socrata:btxj-k9uh · retrieved 2026-08-20
“start_date: 2026-10-19T00:00:00.000”
source.project_id 22962 reported socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 22962”
status Active reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active”
summary The SFMTA Parking Enforcement Headquarters is a planned project to convert the old Animal Care and Control building... generated llm:summarize · retrieved 2026-08-08
“generated from 13 resolved fields; input sha256-v2=4ea4a6c8f04fb9d9b84cc085614209ec68dfc6381a3aab148477855f6ed5052c”

Changes

2026-08-27 field changed immaterial {'type': 'GeometryCollection', 'geometries': [{'type': 'LineString', 'coordinates': [[-122.41261083786333, 37.76753834222235], [-122.41253795609445, 37.766770393356786]]}, {'type': 'Point', 'coordinates': [-122.4125379562634, 37.76677039341892]}, {'type': 'Point', 'coordinates': [-122.41322697966662, 37.76672528389155]}, {'type': 'Point', 'coordinates': [-122.41325982231814, 37.76706997442668]}, {'type': 'LineString', 'coordinates': [[-122.41253795609445, 37.766770393356786], [-122.41282995397762, 37.76675093454198]]}, {'type': 'LineString', 'coordinates': [[-122.41334100384329, 37.76802282248958], [-122.41325982237053, 37.76706997436095]]}]}{'type': 'GeometryCollection', 'geometries': [{'type': 'LineString', 'coordinates': [[-122.41261084, 37.76753834], [-122.41253796, 37.76677039]]}, {'type': 'Point', 'coordinates': [-122.41253796, 37.76677039]}, {'type': 'Point', 'coordinates': [-122.41322698, 37.76672528]}, {'type': 'Point', 'coordinates': [-122.41325982, 37.76706997]}, {'type': 'LineString', 'coordinates': [[-122.41253796, 37.76677039], [-122.41282995, 37.76675093]]}, {'type': 'LineString', 'coordinates': [[-122.413341, 37.76802282], [-122.41325982, 37.76706997]]}]}
2026-08-20 completion date changed 2028-08-012028-10-17
2026-08-20 start date changed 2026-08-032026-10-19
2026-08-08 completion date changed 2027-10-142028-08-01
2026-08-08 start date changed 2025-10-152026-08-03
2026-08-08 field changed immaterial Sanitary Sewer, Land, RoadwaySanitary Sewer

Source records

Public Works coordinated projects (DotMaps) key 22962 primary · rule:dotmaps-group-by-dotmapsid dataset page ↗ · this record’s data ↗

Assertion history (latest 100, including superseded)

PredicateValueClassRecordedState
location.geometry 6 geometries reported 2026-08-27 live
schedule.end 2028-10-17 reported 2026-08-20 live
schedule.start 2026-10-19 reported 2026-08-20 live
summary The SFMTA Parking Enforcement Headquarters is a planned project to convert the old Animal Care and Control building at 1200 15th Street in San Francisco's Mission District into a new headquarters for the SFMTA's Parking and Traffic Enforcement Division. Managed by San Francisco Public Works, the project would seismically retrofit the existing two-story concrete building, replace its mechanical, electrical, plumbing, and fire protection systems to meet current code, and add a new solar photovoltaic panel system. The project is currently in the design phase, with construction scheduled from August 2026 through August 2028, roughly ten months later than originally planned. No cost figures have been published. generated 2026-08-08 live
schedule.end 2028-08-01 reported 2026-08-08 superseded
schedule.start 2026-08-03 reported 2026-08-08 superseded
project_type Sanitary Sewer reported 2026-08-08 live
summary The SFMTA Parking Enforcement Headquarters is a planned City project to convert the former Animal Care and Control building at 1200 15th Street, in San Francisco's Mission District, into a new headquarters for SFMTA's Parking and Traffic Enforcement Division. Managed by San Francisco Public Works, the project would seismically retrofit the existing two-story concrete building, replace its mechanical, electrical, plumbing, and fire-protection systems to meet current code, and add a new rooftop solar panel system. The project is currently in the design phase, with construction-related work scheduled to run from October 2025 through October 2027. No cost figures have been published. generated 2026-07-18 superseded
location.geometry 6 geometries reported 2026-07-17 superseded
location.street_limits 15th St; 15th St from Alabama St to Treat Ave; Alabama St from Treat Ave to 15th St; Harrison St from Alameda St to 15th St derived 2026-07-17 live
schedule.end 2027-10-14 reported 2026-07-17 superseded
schedule.start 2025-10-15 reported 2026-07-17 superseded
source.project_id 22962 reported 2026-07-17 live
contact.email Michael.Rossetto@sfdpw.org reported 2026-07-17 live
contact.name Michael Rossetto reported 2026-07-17 live
agency.owner SF DPW BDC - Building Project Management reported 2026-07-17 live
project_type Sanitary Sewer, Land, Roadway reported 2026-07-17 superseded
phase Design reported 2026-07-17 live
status Active reported 2026-07-17 live
description The Proposed Project Scope: The proposed project scope is to create a new headquarters for SFMTA’s Parking and Traffic Enforcement Division at 1200 - 15th Street in the old Animal Care and Control (ACC) building after its rehabilitation. The existing two-story concrete building will be seismically retrofitted and building systems such as Mechanical, Electrical, Plumbing and Fire Protection will be replaced to meet the current building code. In addition, a new solar photovoltaic panel system will reported 2026-07-17 live