Various Locations Pavement Renovation No 68
candidate project
Construction
5ee0d24d-0ecd-4595-b224-d5125050e97a
San Francisco Public Works is repaving streets at various locations across the city under its Various Locations Pavement Renovation No. 68 project. The active roadway project covers a dozen segments, including stretches of Holloway Avenue, Arellano Avenue and Jennings Street. Construction began in August 2024 and is expected to finish by the end of September 2026, about two months later than an earlier target.AI-generated
Updates (1)
What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.
-
detected Aug 14, 2026Recorded changeExpected completion changedExpected completion: 2026-07-30 → 2026-09-30
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Paul.Barradas@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Paul.Barradas@sfdpw.org” |
| contact.name | Paul Barradas |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Paul Barradas” |
| description | 1947I |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: 1947I” |
| location.geometry | 12 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“12 published segment geometries” |
| location.street_limits | Arellano Ave from Serrano Dr to Holloway Ave; Bright St; Broadmoor Dr; Cargo Way; Holloway Ave; Holloway Ave from Arellano Ave to Tapia Dr; Jennings St from Burke Ave to Newhall St; Jennings St from Cargo Way to Burke Ave; Lake Merced Blvd; Stonecrest Dr; Varela Ave from Holloway Ave to Crespi Dr \ Serrano Dr |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Various Locations Pavement Renovation No 68 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Various Locations Pavement Renovation No 68” |
| phase | Construction |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Construction” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2026-09-30 |
reported
socrata:btxj-k9uh · retrieved 2026-08-14
“end_date: 2026-09-30T00:00:00.000” |
| schedule.start | 2024-08-05 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2024-08-05T00:00:00.000” |
| source.project_id | 31562 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 31562” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | San Francisco Public Works is repaving streets at various locations across the city under its Various Locations... |
generated
llm:summarize · retrieved 2026-08-14
“generated from 13 resolved fields; input sha256-v2=14135fe9cfe028f336c52e570bc04e32444ceed91a0ad29f857f67a741d2ece5” |
Changes
| 2026-08-27 | field changed immaterial | |
| 2026-08-14 | completion date changed |
Source records
| Public Works coordinated projects (DotMaps) | key 31562 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 12 geometries | reported | 2026-08-27 | live |
| summary | San Francisco Public Works is repaving streets at various locations across the city under its Various Locations Pavement Renovation No. 68 project. The active roadway project covers a dozen segments, including stretches of Holloway Avenue, Arellano Avenue and Jennings Street. Construction began in August 2024 and is expected to finish by the end of September 2026, about two months later than an earlier target. | generated | 2026-08-14 | live |
| schedule.end | 2026-09-30 | reported | 2026-08-14 | live |
| summary | Various Locations Pavement Renovation No. 68 is a street repaving project managed by San Francisco Public Works, resurfacing roadway segments across several parts of the city, including stretches of Holloway Avenue, Jennings Street, and Arellano Avenue near Lake Merced. The project is in construction, with work scheduled from August 2024 to July 2026. No cost figures have been published, and the information here is stale — the underlying record has since disappeared from the city's project data, so its current status cannot be confirmed. | generated | 2026-07-31 | superseded |
| summary | This is a road repaving project managed by San Francisco Public Works that is repaving pavement at multiple locations across the city, including stretches of Holloway Avenue, Jennings Street, Lake Merced Boulevard, and several nearby streets. The project is currently in the construction phase, which began in August 2024 and is scheduled to finish by the end of July 2026. No cost figures have been published. | generated | 2026-07-18 | superseded |
| location.geometry | 12 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | Arellano Ave from Serrano Dr to Holloway Ave; Bright St; Broadmoor Dr; Cargo Way; Holloway Ave; Holloway Ave from Arellano Ave to Tapia Dr; Jennings St from Burke Ave to Newhall St; Jennings St from Cargo Way to Burke Ave; Lake Merced Blvd; Stonecrest Dr; Varela Ave from Holloway Ave to Crespi Dr \ Serrano Dr | derived | 2026-07-17 | live |
| schedule.end | 2026-07-30 | reported | 2026-07-17 | superseded |
| schedule.start | 2024-08-05 | reported | 2026-07-17 | live |
| source.project_id | 31562 | reported | 2026-07-17 | live |
| contact.email | Paul.Barradas@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Paul Barradas | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Construction | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | 1947I | reported | 2026-07-17 | live |
| name | Various Locations Pavement Renovation No 68 | reported | 2026-07-17 | live |