Contract 35: Traffic Signal Modifications
candidate project
Construction
efd08f14-333c-46f3-8ef4-917e523076eb
This is a citywide traffic safety project run by the San Francisco Municipal Transportation Agency to design and build signal improvements at 23 intersections selected primarily for pedestrian safety concerns. Planned work includes new pedestrian countdown signals, mast-arm signals to improve visibility, and left-turn or other signal-phasing changes based on collision analysis. The project recently moved into its construction phase, which is scheduled to run from April 2026 through February 2028. No cost figures have been published.AI-generated
Updates (2)
What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.
-
detected Aug 8, 2026Recorded changeExpected completion changedExpected completion: 2027-11-30 → 2028-02-29
-
detected Aug 8, 2026Recorded changePhase changedPhase: Design → Construction
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF MTA SS - Transportation Engineering (Capital) |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF MTA SS - Transportation Engineering (Capital)” |
| description | Design and construct signal improvements at 23 intersections citywide to address safety or operational concerns. These locations have been selected primarily due to pedestrian safety concerns. Improvements will likely include installing new pedestrian countdown signals, installing new mast-arm signals to improve visibility, or implementing left-turn signals or other phasing improvements as-needed per review of a collision analysis. |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: Design and construct signal improvements at 23 intersections citywide to address safety or operational concerns. These locations have been...” |
| location.geometry | 17 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“17 published segment geometries” |
| name | Contract 35: Traffic Signal Modifications |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Contract 35: Traffic Signal Modifications” |
| phase | Construction |
reported
socrata:btxj-k9uh · retrieved 2026-08-08
“project_phase: Construction” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2028-02-29 |
reported
socrata:btxj-k9uh · retrieved 2026-08-08
“end_date: 2028-02-29T00:00:00.000” |
| schedule.start | 2026-04-02 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2026-04-02T00:00:00.000” |
| source.project_id | 8514 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 8514” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | This is a citywide traffic safety project run by the San Francisco Municipal Transportation Agency to design and... |
generated
llm:summarize · retrieved 2026-08-08
“generated from 10 resolved fields; input sha256-v2=730d92943ae5f60b483a4b74d526e8330ae40d4f5bbf650dd9b968675162f391” |
Changes
| 2026-08-27 | field changed immaterial | |
| 2026-08-08 | completion date changed | |
| 2026-08-08 | phase changed |
Source records
| Public Works coordinated projects (DotMaps) | key 8514 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 17 geometries | reported | 2026-08-27 | live |
| summary | This is a citywide traffic safety project run by the San Francisco Municipal Transportation Agency to design and build signal improvements at 23 intersections selected primarily for pedestrian safety concerns. Planned work includes new pedestrian countdown signals, mast-arm signals to improve visibility, and left-turn or other signal-phasing changes based on collision analysis. The project recently moved into its construction phase, which is scheduled to run from April 2026 through February 2028. No cost figures have been published. | generated | 2026-08-08 | live |
| schedule.end | 2028-02-29 | reported | 2026-08-08 | live |
| phase | Construction | reported | 2026-08-08 | live |
| summary | The Contract 35: Traffic Signal Modifications is a citywide roadway safety project led by the SF MTA's Transportation Engineering division that will design and construct signal improvements at 23 intersections chosen primarily to address pedestrian safety concerns. Planned upgrades include new pedestrian countdown signals, mast-arm signals to improve visibility, and left-turn or other signal-phasing changes based on a collision analysis. The project is currently in the design phase, with construction scheduled to run from April 2026 to November 2027. No cost figures have been published. | generated | 2026-07-17 | superseded |
| location.geometry | 17 geometries | reported | 2026-07-17 | superseded |
| schedule.end | 2027-11-30 | reported | 2026-07-17 | superseded |
| schedule.start | 2026-04-02 | reported | 2026-07-17 | live |
| source.project_id | 8514 | reported | 2026-07-17 | live |
| agency.owner | SF MTA SS - Transportation Engineering (Capital) | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | superseded |
| status | Active | reported | 2026-07-17 | live |
| description | Design and construct signal improvements at 23 intersections citywide to address safety or operational concerns. These locations have been selected primarily due to pedestrian safety concerns. Improvements will likely include installing new pedestrian countdown signals, installing new mast-arm signals to improve visibility, or implementing left-turn signals or other phasing improvements as-needed per review of a collision analysis. | reported | 2026-07-17 | live |
| name | Contract 35: Traffic Signal Modifications | reported | 2026-07-17 | live |