PW Various Locations Sewer Replacement No 21
candidate project
Design
702551b1-aaf6-4b71-826f-440d639f25f8
This is a sanitary sewer replacement project managed by San Francisco Public Works, covering roughly two dozen street segments in the Richmond District across avenues from 6th to 44th, including stretches of Balboa, Cabrillo, Clement, and Geary. The project is currently in the design phase, with construction scheduled to run from October 2026 to October 2027. No cost figures have been published.AI-generated
Updates (2)
What has happened on this project: the agency's own announcements, documents it published, changes we detected in its records, and independent coverage. Each entry says where it came from.
-
detected Aug 11, 2026Recorded changeExpected completion changedExpected completion: 2027-07-18 → 2027-10-02
-
detected Aug 11, 2026Recorded changeStart changedStart: 2026-07-18 → 2026-10-02
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Hydraulic |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Hydraulic” |
| contact.email | Lesley.Wong@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Lesley.Wong@sfdpw.org” |
| contact.name | Lesley Wong |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Lesley Wong” |
| description | 2469i |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: 2469i” |
| location.geometry | 24 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“24 published segment geometries” |
| location.street_limits | 06th Ave; 06th Ave from Clement St to Geary Blvd; 07th Ave; 09th Ave from Balboa St to Cabrillo St; 15th Ave; 16th Ave; 16th Ave from Lake St to California St; 19th Ave; 19th Ave from Balboa St to Cabrillo St; 28th Ave; 28th Ave from California St to Clement St; 34th Ave; 34th Ave from Anza St to Balboa St; 36th Ave; 36th Ave from Anza St to Balboa St; 43rd Ave; 44th Ave; Balboa St from 06th Ave to 07th Ave; Cabrillo St from 15th Ave to 16th Ave; Cabrillo St from 43rd Ave to 44th Ave … |
derived
socrata:btxj-k9uh · retrieved 2026-08-11
“assembled from segment on/from/to street fields” |
| name | PW Various Locations Sewer Replacement No 21 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: PW Various Locations Sewer Replacement No 21” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Sanitary Sewer |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“facility_type: Sanitary Sewer” |
| schedule.end | 2027-10-02 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“end_date: 2027-10-02T00:00:00.000” |
| schedule.start | 2026-10-02 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“start_date: 2026-10-02T00:00:00.000” |
| source.project_id | 31368 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 31368” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | This is a sanitary sewer replacement project managed by San Francisco Public Works, covering roughly two dozen... |
generated
llm:summarize · retrieved 2026-08-11
“generated from 13 resolved fields; input sha256-v2=db9ca7d502e07edaae12f2409d26640898d33bb2bdc95ed59a75352a541dbe97” |
Changes
| 2026-08-27 | field changed immaterial | |
| 2026-08-11 | field changed immaterial | |
| 2026-08-11 | field changed immaterial | |
| 2026-08-11 | completion date changed | |
| 2026-08-11 | start date changed | |
| 2026-08-11 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 31368 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 24 geometries | reported | 2026-08-27 | live |
| summary | This is a sanitary sewer replacement project managed by San Francisco Public Works, covering roughly two dozen street segments in the Richmond District across avenues from 6th to 44th, including stretches of Balboa, Cabrillo, Clement, and Geary. The project is currently in the design phase, with construction scheduled to run from October 2026 to October 2027. No cost figures have been published. | generated | 2026-08-11 | live |
| location.geometry | 24 geometries | reported | 2026-08-11 | superseded |
| location.street_limits | 06th Ave; 06th Ave from Clement St to Geary Blvd; 07th Ave; 09th Ave from Balboa St to Cabrillo St; 15th Ave; 16th Ave; 16th Ave from Lake St to California St; 19th Ave; 19th Ave from Balboa St to Cabrillo St; 28th Ave; 28th Ave from California St to Clement St; 34th Ave; 34th Ave from Anza St to Balboa St; 36th Ave; 36th Ave from Anza St to Balboa St; 43rd Ave; 44th Ave; Balboa St from 06th Ave to 07th Ave; Cabrillo St from 15th Ave to 16th Ave; Cabrillo St from 43rd Ave to 44th Ave … | derived | 2026-08-11 | live |
| schedule.end | 2027-10-02 | reported | 2026-08-11 | live |
| schedule.start | 2026-10-02 | reported | 2026-08-11 | live |
| project_type | Sanitary Sewer | reported | 2026-08-11 | live |
| summary | This is a sanitary sewer and roadway project in San Francisco's Richmond District, replacing aging sewer lines across roughly 28 street segments spanning the numbered avenues (such as 6th, 16th, and 19th Avenues) between cross streets like Anza, Balboa, and Cabrillo. Owned by San Francisco Public Works (Hydraulic Infrastructure Design Division), the project is currently active in the design phase, with construction scheduled to run from July 2026 to July 2027. No cost figures have been published. | generated | 2026-07-18 | superseded |
| location.geometry | 28 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | 06th Ave; 06th Ave from Clement St to Geary Blvd; 07th Ave; 09th Ave from Balboa St to Cabrillo St; 15th Ave; 16th Ave; 16th Ave from Lake St to California St; 18th Ave; 18th Ave from Anza St to Balboa St; 19th Ave; 19th Ave from Anza St to Balboa St; 19th Ave from Balboa St to Cabrillo St; 28th Ave; 28th Ave from California St to Clement St; 34th Ave; 34th Ave from Anza St to Balboa St; 36th Ave; 36th Ave from Anza St to Balboa St; 43rd Ave; 44th Ave … | derived | 2026-07-17 | superseded |
| schedule.end | 2027-07-18 | reported | 2026-07-17 | superseded |
| schedule.start | 2026-07-18 | reported | 2026-07-17 | superseded |
| source.project_id | 31368 | reported | 2026-07-17 | live |
| contact.email | Lesley.Wong@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Lesley Wong | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Hydraulic | reported | 2026-07-17 | live |
| project_type | Sanitary Sewer, Roadway | reported | 2026-07-17 | superseded |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | 2469i | reported | 2026-07-17 | live |
| name | PW Various Locations Sewer Replacement No 21 | reported | 2026-07-17 | live |