7th St, 8th St and Folsom St Pavement Renovation
candidate project
Planning
Pre-Planning
f2eeec61-ee67-433c-90d2-d25d51a322c3
The 7th St, 8th St and Folsom St Pavement Renovation is a proposed roadway repaving project led by San Francisco Public Works, covering numerous street segments across the South of Market and Mission areas, including stretches of 7th, 8th, and Folsom streets. The project is in early pre-planning, with construction tentatively scheduled to run from mid-2030 to September 2031. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Edmund.Lee@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Edmund.Lee@sfdpw.org” |
| contact.name | Edmund Lee |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Edmund Lee” |
| location.geometry | 49 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“49 published segment geometries” |
| location.street_limits | 07th St; 07th St from Brannan St to Townsend St; 07th St from Bryant St to Brannan St; 07th St from Cleveland St to Harrison St; 07th St from Folsom St to Cleveland St; 07th St from Howard St to Folsom St; 07th St from Minna St to Natoma St; 07th St from Mission St to Minna St; 07th St from Natoma St to Howard St; 08th St; 08th St from Folsom St to Ringold St; 08th St from Heron St to Harrison St; 08th St from Ringold St to Heron St; 12th St; 14th St; 15th St; 18th St; 18th St from Harrison St to Treat Ave; 18th St from Treat Ave to Folsom St; 19th St … |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | 7th St, 8th St and Folsom St Pavement Renovation |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: 7th St, 8th St and Folsom St Pavement Renovation” |
| phase | Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2031-09-10 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2031-09-10T00:00:00.000” |
| schedule.start | 2030-06-28 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2030-06-28T00:00:00.000” |
| source.project_id | 35255 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 35255” |
| status | Pre-Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Pre-Planning” |
| summary | The 7th St, 8th St and Folsom St Pavement Renovation is a proposed roadway repaving project led by San Francisco... |
generated
llm:summarize · retrieved 2026-07-18
“generated from 12 resolved fields; input sha256-v2=4eb3678dc5298b6d06b9ea6ecb57fcd08a7dcb13775e7e0c0de9165a7115c619” |
Changes
| 2026-08-27 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 35255 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 49 geometries | reported | 2026-08-27 | live |
| summary | The 7th St, 8th St and Folsom St Pavement Renovation is a proposed roadway repaving project led by San Francisco Public Works, covering numerous street segments across the South of Market and Mission areas, including stretches of 7th, 8th, and Folsom streets. The project is in early pre-planning, with construction tentatively scheduled to run from mid-2030 to September 2031. No cost figures have been published. | generated | 2026-07-18 | live |
| location.geometry | 49 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | 07th St; 07th St from Brannan St to Townsend St; 07th St from Bryant St to Brannan St; 07th St from Cleveland St to Harrison St; 07th St from Folsom St to Cleveland St; 07th St from Howard St to Folsom St; 07th St from Minna St to Natoma St; 07th St from Mission St to Minna St; 07th St from Natoma St to Howard St; 08th St; 08th St from Folsom St to Ringold St; 08th St from Heron St to Harrison St; 08th St from Ringold St to Heron St; 12th St; 14th St; 15th St; 18th St; 18th St from Harrison St to Treat Ave; 18th St from Treat Ave to Folsom St; 19th St … | derived | 2026-07-17 | live |
| schedule.end | 2031-09-10 | reported | 2026-07-17 | live |
| schedule.start | 2030-06-28 | reported | 2026-07-17 | live |
| source.project_id | 35255 | reported | 2026-07-17 | live |
| contact.email | Edmund.Lee@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Edmund Lee | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | live |
| status | Pre-Planning | reported | 2026-07-17 | live |
| name | 7th St, 8th St and Folsom St Pavement Renovation | reported | 2026-07-17 | live |