Various Locations Pavement Renovation No 71A
candidate project
Construction
ad503323-8887-491a-b43f-b0874d7acdd0
This is an active street repaving project managed by San Francisco Public Works (Streets & Highways division) covering roughly 20 street segments across the city, including portions of Clay, Davis, Drumm, Chestnut, and Lombard streets. The roadway renovation work is currently in construction, with work having started in March 2025 and expected to be completed by September 2026. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Paul.Barradas@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“project_manager_email: Paul.Barradas@sfdpw.org” |
| contact.name | Paul Barradas |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“project_manager_name: Paul Barradas” |
| description | 2276I |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“description: 2276I” |
| location.geometry | 20 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“20 published segment geometries” |
| location.street_limits | Chestnut St; Clay St; Clay St from Drumm St to Davis St; Clay St from Mason St to Sproule Ln; Clay St from Sproule Ln to Taylor St; Commercial St; Davis St from Beale St \ Market St \ Pine St to California St; Davis St from California St to Sacramento St; Davis St from Sacramento St to Clay St; Drumm St; Drumm St from Sacramento St to Clay St; Eastman St from Russell St to Rockland St; Francisco St; Fresno St; Grant Ave; Greenwich St; Lombard St |
derived
socrata:btxj-k9uh · retrieved 2026-08-11
“assembled from segment on/from/to street fields” |
| name | Various Locations Pavement Renovation No 71A |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“name: Various Locations Pavement Renovation No 71A” |
| phase | Construction |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“project_phase: Construction” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“facility_type: Roadway” |
| schedule.end | 2026-09-06 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“end_date: 2026-09-06T00:00:00.000” |
| schedule.start | 2025-03-03 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“start_date: 2025-03-03T00:00:00.000” |
| source.project_id | 23957 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“dotmapsid: 23957” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“project_status: Active” |
| summary | This is an active street repaving project managed by San Francisco Public Works (Streets & Highways division)... |
generated
llm:summarize · retrieved 2026-08-11
“generated from 13 resolved fields; input sha256-v2=5587d3d67076cb581c25f569f723cf700a4a5ef659a897e80e0d761f50ba173a” |
Changes
| 2026-08-27 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 23957 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 20 geometries | reported | 2026-08-27 | live |
| summary | This is an active street repaving project managed by San Francisco Public Works (Streets & Highways division) covering roughly 20 street segments across the city, including portions of Clay, Davis, Drumm, Chestnut, and Lombard streets. The roadway renovation work is currently in construction, with work having started in March 2025 and expected to be completed by September 2026. No cost figures have been published. | generated | 2026-08-11 | live |
| location.geometry | 20 geometries | reported | 2026-08-11 | superseded |
| location.street_limits | Chestnut St; Clay St; Clay St from Drumm St to Davis St; Clay St from Mason St to Sproule Ln; Clay St from Sproule Ln to Taylor St; Commercial St; Davis St from Beale St \ Market St \ Pine St to California St; Davis St from California St to Sacramento St; Davis St from Sacramento St to Clay St; Drumm St; Drumm St from Sacramento St to Clay St; Eastman St from Russell St to Rockland St; Francisco St; Fresno St; Grant Ave; Greenwich St; Lombard St | derived | 2026-08-11 | live |
| schedule.end | 2026-09-06 | reported | 2026-08-11 | live |
| schedule.start | 2025-03-03 | reported | 2026-08-11 | live |
| source.project_id | 23957 | reported | 2026-08-11 | live |
| contact.email | Paul.Barradas@sfdpw.org | reported | 2026-08-11 | live |
| contact.name | Paul Barradas | reported | 2026-08-11 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-08-11 | live |
| project_type | Roadway | reported | 2026-08-11 | live |
| phase | Construction | reported | 2026-08-11 | live |
| status | Active | reported | 2026-08-11 | live |
| description | 2276I | reported | 2026-08-11 | live |
| name | Various Locations Pavement Renovation No 71A | reported | 2026-08-11 | live |