Stormwater Trash Capture

candidate project Design a8209017-64ca-4665-ad6c-de0139271a58

Current record

FieldValueProvenance
agency.owner SF DPW IDC - Hydraulic reported socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Hydraulic”
contact.email Lesley.Wong@sfdpw.org reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Lesley.Wong@sfdpw.org”
contact.name Lesley Wong reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Lesley Wong”
description 2492i_Installation of high flow trash capture systems at 7 sites within Port Jurisdiction with the objective to reduce trash discharges into San Francisco Bay Waters. reported socrata:btxj-k9uh · retrieved 2026-07-17
“description: 2492i_Installation of high flow trash capture systems at 7 sites within Port Jurisdiction with the objective to reduce trash discharges into...”
location.geometry 24 geometries reported socrata:btxj-k9uh · retrieved 2026-07-17
“24 published segment geometries”
location.street_limits 26th St; Amador St; Cargo Way; Chestnut St; Error; Folsom St; Harrison St; Howard St; Maryland St from 26th St to Cesar Chavez St; Mission St; Taylor St; The Embarcadero; The Embarcadero from Don Chee Way to Washington St; The Embarcadero from Folsom St to Howard St; The Embarcadero from Howard St to Mission St; The Embarcadero from Jefferson St \ Powell St to Taylor St; The Embarcadero from Mission St to Don Chee Way; The Embarcadero from Mission St to Washington St derived socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields”
name Stormwater Trash Capture reported socrata:btxj-k9uh · retrieved 2026-07-17
“name: Stormwater Trash Capture”
phase Design reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design”
project_type Sanitary Sewer reported socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Sanitary Sewer”
schedule.end 2028-03-24 reported socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2028-03-24T00:00:00.000”
schedule.start 2027-06-28 reported socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2027-06-28T00:00:00.000”
source.project_id 34913 reported socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 34913”
status Active reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active”

Source records

Public Works coordinated projects (DotMaps) key 34913 primary · rule:dotmaps-group-by-dotmapsid dataset page ↗ · this record’s data ↗

Assertion history (latest 100, including superseded)

PredicateValueClassRecordedState
location.geometry 24 geometries reported 2026-07-17 live
location.street_limits 26th St; Amador St; Cargo Way; Chestnut St; Error; Folsom St; Harrison St; Howard St; Maryland St from 26th St to Cesar Chavez St; Mission St; Taylor St; The Embarcadero; The Embarcadero from Don Chee Way to Washington St; The Embarcadero from Folsom St to Howard St; The Embarcadero from Howard St to Mission St; The Embarcadero from Jefferson St \ Powell St to Taylor St; The Embarcadero from Mission St to Don Chee Way; The Embarcadero from Mission St to Washington St derived 2026-07-17 live
schedule.end 2028-03-24 reported 2026-07-17 live
schedule.start 2027-06-28 reported 2026-07-17 live
source.project_id 34913 reported 2026-07-17 live
contact.email Lesley.Wong@sfdpw.org reported 2026-07-17 live
contact.name Lesley Wong reported 2026-07-17 live
agency.owner SF DPW IDC - Hydraulic reported 2026-07-17 live
project_type Sanitary Sewer reported 2026-07-17 live
phase Design reported 2026-07-17 live
status Active reported 2026-07-17 live
description 2492i_Installation of high flow trash capture systems at 7 sites within Port Jurisdiction with the objective to reduce trash discharges into San Francisco Bay Waters. reported 2026-07-17 live
name Stormwater Trash Capture reported 2026-07-17 live