Northern Waterfront Electrical Improvements (NWEI)

candidate project Planning Pre-Planning 93681791-3807-420e-9a66-872c612daf9e

Current record

FieldValueProvenance
agency.owner SF PUC Power reported socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF PUC Power”
description The project will expand Power Enterprise’s electrical network by building a new switchyard at sea wall lot 328 and constructing duct banks from PG&E substation to SWL 328 and from SWL 328 to the Downtown Ferry Terminal. A future Phase 2 of this project would construct a new substation at SWL 328 and extend duct banks from SWL 328 to SFPUC switchyard located at Embarcadero/Bay St. reported socrata:btxj-k9uh · retrieved 2026-07-17
“description: The project will expand Power Enterprise’s electrical network by building a new switchyard at sea wall lot 328 and constructing duct banks from...”
location.geometry 9 geometries reported socrata:btxj-k9uh · retrieved 2026-07-17
“9 published segment geometries”
location.street_limits BEALE ST from FOLSOM ST to HARRISON ST; FOLSOM ST; FREMONT ST from FOLSOM ST to HARRISON ST; HARRISON ST from FREMONT ST to THE EMBARCADERO; HOWARD ST from SPEAR ST to THE EMBARCADERO; MAIN ST from FOLSOM ST to HARRISON ST; MISSION ST from SPEAR ST to THE EMBARCADERO; SPEAR ST from END: 400-499 BLOCK to MISSION ST; THE EMBARCADERO from BRYANT ST to BAY ST derived socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields”
name Northern Waterfront Electrical Improvements (NWEI) reported socrata:btxj-k9uh · retrieved 2026-07-17
“name: Northern Waterfront Electrical Improvements (NWEI)”
phase Planning reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning”
project_type Power reported socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Power”
schedule.end 2026-12-31 reported socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2026-12-31T00:00:00.000”
schedule.start 2023-04-01 reported socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2023-04-01T00:00:00.000”
source.project_id 11336 reported socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 11336”
status Pre-Planning reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Pre-Planning”

Source records

Public Works coordinated projects (DotMaps) key 11336 primary · rule:dotmaps-group-by-dotmapsid dataset page ↗ · this record’s data ↗

Assertion history (latest 100, including superseded)

PredicateValueClassRecordedState
location.geometry 9 geometries reported 2026-07-17 live
location.street_limits BEALE ST from FOLSOM ST to HARRISON ST; FOLSOM ST; FREMONT ST from FOLSOM ST to HARRISON ST; HARRISON ST from FREMONT ST to THE EMBARCADERO; HOWARD ST from SPEAR ST to THE EMBARCADERO; MAIN ST from FOLSOM ST to HARRISON ST; MISSION ST from SPEAR ST to THE EMBARCADERO; SPEAR ST from END: 400-499 BLOCK to MISSION ST; THE EMBARCADERO from BRYANT ST to BAY ST derived 2026-07-17 live
schedule.end 2026-12-31 reported 2026-07-17 live
schedule.start 2023-04-01 reported 2026-07-17 live
source.project_id 11336 reported 2026-07-17 live
agency.owner SF PUC Power reported 2026-07-17 live
project_type Power reported 2026-07-17 live
phase Planning reported 2026-07-17 live
status Pre-Planning reported 2026-07-17 live
description The project will expand Power Enterprise’s electrical network by building a new switchyard at sea wall lot 328 and constructing duct banks from PG&E substation to SWL 328 and from SWL 328 to the Downtown Ferry Terminal. A future Phase 2 of this project would construct a new substation at SWL 328 and extend duct banks from SWL 328 to SFPUC switchyard located at Embarcadero/Bay St. reported 2026-07-17 live
name Northern Waterfront Electrical Improvements (NWEI) reported 2026-07-17 live