1819-004: 12- inch Water Main Rehabilitation and 8-inch Water Main Replacement on 19th Street from Pennsylvania to Wisconsin, on Wisconsin from 19th St to 22nd St, and on Various Local Area Streets
candidate project
Planning
Pre-Planning
8b47fbcd-90c3-4d09-9fa1-11840528999d
This is a San Francisco Public Utilities Commission water project to rehabilitate 12-inch water mains and replace 8-inch water mains in the Potrero Hill area, centered on 19th Street between Pennsylvania Avenue and Wisconsin Street, along Wisconsin Street, and on various nearby local streets. The project is in early pre-planning, with construction scheduled to run from January 2027 through June 2028. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF PUC Water |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF PUC Water” |
| description | 12- inch Water Main Rehabilitation and 8-inch Water Main Replacement on 19th Street from Pennsylvania to Wisconsin, on Wisconsin from 19th St to 22nd St, and on Various Local Area Streets |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: 12- inch Water Main Rehabilitation and 8-inch Water Main Replacement on 19th Street from Pennsylvania to Wisconsin, on Wisconsin from 19th St...” |
| location.geometry | 7 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“7 published segment geometries” |
| location.street_limits | 19TH ST from WISCONSIN ST to PENNSYLVANIA AVE; ARKANSAS ST; MISSISSIPPI ST; MISSOURI ST; PENNSYLVANIA AVE; TEXAS ST from SIERRA ST to 20TH ST; WISCONSIN ST from 19TH ST to 22ND ST |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | 1819-004: 12- inch Water Main Rehabilitation and 8-inch Water Main Replacement on 19th Street from Pennsylvania to Wisconsin, on Wisconsin from 19th St to 22nd St, and on Various Local Area Streets |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: 1819-004: 12- inch Water Main Rehabilitation and 8-inch Water Main Replacement on 19th Street from Pennsylvania to Wisconsin, on Wisconsin from 19th...” |
| phase | Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning” |
| project_type | Water |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Water” |
| schedule.end | 2028-06-30 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2028-06-30T00:00:00.000” |
| schedule.start | 2027-01-01 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2027-01-01T00:00:00.000” |
| source.project_id | 9104 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 9104” |
| status | Pre-Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Pre-Planning” |
| summary | This is a San Francisco Public Utilities Commission water project to rehabilitate 12-inch water mains and replace... |
generated
llm:summarize · retrieved 2026-07-17
“generated from 11 resolved fields; input sha256-v2=14aebf51b5eae7c0ed4e8ac0fd80ea98bd02d3140408760bd8f180ae3bd733c8” |
Source records
| Public Works coordinated projects (DotMaps) | key 9104 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| summary | This is a San Francisco Public Utilities Commission water project to rehabilitate 12-inch water mains and replace 8-inch water mains in the Potrero Hill area, centered on 19th Street between Pennsylvania Avenue and Wisconsin Street, along Wisconsin Street, and on various nearby local streets. The project is in early pre-planning, with construction scheduled to run from January 2027 through June 2028. No cost figures have been published. | generated | 2026-07-17 | live |
| location.geometry | 7 geometries | reported | 2026-07-17 | live |
| location.street_limits | 19TH ST from WISCONSIN ST to PENNSYLVANIA AVE; ARKANSAS ST; MISSISSIPPI ST; MISSOURI ST; PENNSYLVANIA AVE; TEXAS ST from SIERRA ST to 20TH ST; WISCONSIN ST from 19TH ST to 22ND ST | derived | 2026-07-17 | live |
| schedule.end | 2028-06-30 | reported | 2026-07-17 | live |
| schedule.start | 2027-01-01 | reported | 2026-07-17 | live |
| source.project_id | 9104 | reported | 2026-07-17 | live |
| agency.owner | SF PUC Water | reported | 2026-07-17 | live |
| project_type | Water | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | live |
| status | Pre-Planning | reported | 2026-07-17 | live |
| description | 12- inch Water Main Rehabilitation and 8-inch Water Main Replacement on 19th Street from Pennsylvania to Wisconsin, on Wisconsin from 19th St to 22nd St, and on Various Local Area Streets | reported | 2026-07-17 | live |
| name | 1819-004: 12- inch Water Main Rehabilitation and 8-inch Water Main Replacement on 19th Street from Pennsylvania to Wisconsin, on Wisconsin from 19th St to 22nd St, and on Various Local Area Streets | reported | 2026-07-17 | live |