Contract 66: New Traffic Signals
candidate project
Design
87045688-e885-4139-a0b3-48e1a332d3d3
A San Francisco Municipal Transportation Agency project, Contract 66: New Traffic Signals will install new traffic signals—including poles, signals, street lighting, pedestrian countdown signals, and accessible pedestrian signals—along with new ADA-compliant curb ramps where they don't already exist. The work spans multiple locations across the city, including stretches of Cesar Chavez Street, Fulton Street, and Lincoln Way. The project is currently in the design phase, with construction scheduled to run from March 2027 to March 2028. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF MTA SS - Transportation Engineering (Capital) |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF MTA SS - Transportation Engineering (Capital)” |
| description | Construct new traffic signals including poles, signals, street lighting, pedestrian countdown signals (PCS), and accessible pedestrian signals (APS) in addition to new ADA compliant curb ramps where they do not already exist. |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: Construct new traffic signals including poles, signals, street lighting, pedestrian countdown signals (PCS), and accessible pedestrian signals...” |
| location.geometry | 11 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“11 published segment geometries” |
| location.street_limits | 28TH ST; 4TH AVE; 4TH ST; CESAR CHAVEZ ST; COTTER ST; FULTON ST; LINCOLN WAY; LONG BRIDGE ST; MINT ST; WALLER ST |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Contract 66: New Traffic Signals |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Contract 66: New Traffic Signals” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Traffic Signals |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Traffic Signals” |
| schedule.end | 2028-03-01 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2028-03-01T00:00:00.000” |
| schedule.start | 2027-03-01 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2027-03-01T00:00:00.000” |
| source.project_id | 9108 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 9108” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | A San Francisco Municipal Transportation Agency project, Contract 66: New Traffic Signals will install new traffic... |
generated
llm:summarize · retrieved 2026-07-17
“generated from 11 resolved fields; input sha256-v2=90a5dd149bbb29f9d2660e4838468bb53be19f0ae14669d2526dd10946225d51” |
Source records
| Public Works coordinated projects (DotMaps) | key 9108 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| summary | A San Francisco Municipal Transportation Agency project, Contract 66: New Traffic Signals will install new traffic signals—including poles, signals, street lighting, pedestrian countdown signals, and accessible pedestrian signals—along with new ADA-compliant curb ramps where they don't already exist. The work spans multiple locations across the city, including stretches of Cesar Chavez Street, Fulton Street, and Lincoln Way. The project is currently in the design phase, with construction scheduled to run from March 2027 to March 2028. No cost figures have been published. | generated | 2026-07-17 | live |
| location.geometry | 11 geometries | reported | 2026-07-17 | live |
| location.street_limits | 28TH ST; 4TH AVE; 4TH ST; CESAR CHAVEZ ST; COTTER ST; FULTON ST; LINCOLN WAY; LONG BRIDGE ST; MINT ST; WALLER ST | derived | 2026-07-17 | live |
| schedule.end | 2028-03-01 | reported | 2026-07-17 | live |
| schedule.start | 2027-03-01 | reported | 2026-07-17 | live |
| source.project_id | 9108 | reported | 2026-07-17 | live |
| agency.owner | SF MTA SS - Transportation Engineering (Capital) | reported | 2026-07-17 | live |
| project_type | Traffic Signals | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | Construct new traffic signals including poles, signals, street lighting, pedestrian countdown signals (PCS), and accessible pedestrian signals (APS) in addition to new ADA compliant curb ramps where they do not already exist. | reported | 2026-07-17 | live |
| name | Contract 66: New Traffic Signals | reported | 2026-07-17 | live |