12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr. to Cabrillo St., and on Various Street Locations
candidate project
Design
Started
81a8f651-3174-49ca-87c4-1485c665e47b
The San Francisco Public Utilities Commission is planning to rehabilitate 12-inch cast iron water mains in the city's Outer Richmond and Sunset areas, primarily along 45th and 47th Avenues and several nearby streets. The water project is currently in the design phase, with construction scheduled to run from February 2027 to February 2028. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF PUC Water |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF PUC Water” |
| contact.email | pdavis@sfwater.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: pdavis@sfwater.org” |
| contact.name | Portia Davis |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Portia Davis” |
| description | 12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr. to Cabrillo St., and on Various Street Locations |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: 12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr....” |
| location.geometry | 7 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“7 published segment geometries” |
| location.street_limits | 47TH AVE from CABRILLO ST to JOHN F KENNEDY DR; CABRILLO ST from 46TH AVE to 47TH AVE; JOHN F KENNEDY DR |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | 12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr. to Cabrillo St., and on Various Street Locations |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: 12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr. to...” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Water |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Water” |
| schedule.end | 2028-02-25 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2028-02-25T00:00:00.000” |
| schedule.start | 2027-02-23 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2027-02-23T00:00:00.000” |
| source.project_id | 9107 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 9107” |
| status | Started |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Started” |
| summary | The San Francisco Public Utilities Commission is planning to rehabilitate 12-inch cast iron water mains in the... |
generated
llm:summarize · retrieved 2026-07-17
“generated from 13 resolved fields; input sha256-v2=d1478ec76b515e0c1367cdb317dc2c5a2484774ccddbcd9e70de085f41e6811a” |
Source records
| Public Works coordinated projects (DotMaps) | key 9107 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| summary | The San Francisco Public Utilities Commission is planning to rehabilitate 12-inch cast iron water mains in the city's Outer Richmond and Sunset areas, primarily along 45th and 47th Avenues and several nearby streets. The water project is currently in the design phase, with construction scheduled to run from February 2027 to February 2028. No cost figures have been published. | generated | 2026-07-17 | live |
| location.geometry | 7 geometries | reported | 2026-07-17 | live |
| location.street_limits | 47TH AVE from CABRILLO ST to JOHN F KENNEDY DR; CABRILLO ST from 46TH AVE to 47TH AVE; JOHN F KENNEDY DR | derived | 2026-07-17 | live |
| schedule.end | 2028-02-25 | reported | 2026-07-17 | live |
| schedule.start | 2027-02-23 | reported | 2026-07-17 | live |
| source.project_id | 9107 | reported | 2026-07-17 | live |
| contact.email | pdavis@sfwater.org | reported | 2026-07-17 | live |
| contact.name | Portia Davis | reported | 2026-07-17 | live |
| agency.owner | SF PUC Water | reported | 2026-07-17 | live |
| project_type | Water | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | live |
| status | Started | reported | 2026-07-17 | live |
| description | 12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr. to Cabrillo St., and on Various Street Locations | reported | 2026-07-17 | live |
| name | 12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr. to Cabrillo St., and on Various Street Locations | reported | 2026-07-17 | live |