PW Minna Natoma Streetscape Sewer Replacement
candidate project
Construction
7fa30b82-e2ff-42d4-9f9b-8c98c313497f
San Francisco Public Works is replacing sewer lines along Minna and Natoma streets between 2nd and 3rd streets in the South of Market area, work funded by the Public Utilities Commission and folded into the larger Minna/Natoma Streetscape project. Owned by Public Works' Hydraulic division, the sanitary sewer project is currently in construction, having begun in May 2025 and scheduled to finish in October 2026.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Hydraulic |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Hydraulic” |
| contact.email | Lesley.Wong@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Lesley.Wong@sfdpw.org” |
| contact.name | Lesley Wong |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Lesley Wong” |
| description | 2234i sewer work funded by PUC to be incorporated into the Minna/Natoma Streetscape project. |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: 2234i sewer work funded by PUC to be incorporated into the Minna/Natoma Streetscape project.” |
| location.geometry | 9 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“9 published segment geometries” |
| location.street_limits | 02nd St; 03rd St; Minna St; Minna St from 02nd St to New Montgomery St; Minna St from New Montgomery St to 03rd St; Natoma St; Natoma St from 02nd St to New Montgomery St; Natoma St from New Montgomery St to End |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | PW Minna Natoma Streetscape Sewer Replacement |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: PW Minna Natoma Streetscape Sewer Replacement” |
| phase | Construction |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Construction” |
| project_type | Sanitary Sewer |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Sanitary Sewer” |
| schedule.end | 2026-10-22 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2026-10-22T00:00:00.000” |
| schedule.start | 2025-05-01 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2025-05-01T00:00:00.000” |
| source.project_id | 53916 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 53916” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | San Francisco Public Works is replacing sewer lines along Minna and Natoma streets between 2nd and 3rd streets in... |
generated
llm:summarize · retrieved 2026-07-18
“generated from 13 resolved fields; input sha256-v2=7421850985aed27c8c5a5966805d623dda3b36dad93568b9b7d2bb00aa80dcba” |
Changes
| 2026-08-27 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 53916 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 9 geometries | reported | 2026-08-27 | live |
| summary | San Francisco Public Works is replacing sewer lines along Minna and Natoma streets between 2nd and 3rd streets in the South of Market area, work funded by the Public Utilities Commission and folded into the larger Minna/Natoma Streetscape project. Owned by Public Works' Hydraulic division, the sanitary sewer project is currently in construction, having begun in May 2025 and scheduled to finish in October 2026. | generated | 2026-07-18 | live |
| location.geometry | 9 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | 02nd St; 03rd St; Minna St; Minna St from 02nd St to New Montgomery St; Minna St from New Montgomery St to 03rd St; Natoma St; Natoma St from 02nd St to New Montgomery St; Natoma St from New Montgomery St to End | derived | 2026-07-17 | live |
| schedule.end | 2026-10-22 | reported | 2026-07-17 | live |
| schedule.start | 2025-05-01 | reported | 2026-07-17 | live |
| source.project_id | 53916 | reported | 2026-07-17 | live |
| contact.email | Lesley.Wong@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Lesley Wong | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Hydraulic | reported | 2026-07-17 | live |
| project_type | Sanitary Sewer | reported | 2026-07-17 | live |
| phase | Construction | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | 2234i sewer work funded by PUC to be incorporated into the Minna/Natoma Streetscape project. | reported | 2026-07-17 | live |
| name | PW Minna Natoma Streetscape Sewer Replacement | reported | 2026-07-17 | live |