Lower Alemany Area Stormwater Improvement Project
candidate project
Design
72ec7f28-efc2-40c6-8f58-80060249ea77
The Lower Alemany Area Stormwater Improvement Project is a San Francisco Public Utilities Commission sewer construction project on the city's south side, running along Alemany Boulevard, Boutwell Street, and Industrial Street. Owned by the SFPUC's Engineering Management Bureau, it involves building a new sewer system including a 5,650-foot, 10-foot-diameter tunnel, a 1,000-foot box sewer, and a 42-inch-diameter sewer. The project is currently active and in the design phase, with construction scheduled to run from January 2027 through June 2031. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF PUC - Engineering Management Bureau |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF PUC - Engineering Management Bureau” |
| description | Construction of a new sewer that consists of 5,650 linear feet of 10-ft diameter tunnel, 1000 linear feet of 20 ft x 9-ft box sewer and 42-in diameter sewer. |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: Construction of a new sewer that consists of 5,650 linear feet of 10-ft diameter tunnel, 1000 linear feet of 20 ft x 9-ft box sewer and 42-in...” |
| location.geometry | 5 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“5 published segment geometries” |
| location.street_limits | ALEMANY BLVD from STONEYBROOK AVE to HWY 101 S OFF RAMP; BOUTWELL ST; INDUSTRIAL ST from LOOMIS ST to BARNEVELD AVE |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Lower Alemany Area Stormwater Improvement Project |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Lower Alemany Area Stormwater Improvement Project” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Combined |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Combined” |
| schedule.end | 2031-06-30 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2031-06-30T00:00:00.000” |
| schedule.start | 2027-01-02 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2027-01-02T00:00:00.000” |
| source.project_id | 8711 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 8711” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | The Lower Alemany Area Stormwater Improvement Project is a San Francisco Public Utilities Commission sewer... |
generated
llm:summarize · retrieved 2026-07-17
“generated from 11 resolved fields; input sha256-v2=798cef6c092812b93c52f9e44d8d73728a5aa6933ee8907be23fa548fd8f42b0” |
Source records
| Public Works coordinated projects (DotMaps) | key 8711 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| summary | The Lower Alemany Area Stormwater Improvement Project is a San Francisco Public Utilities Commission sewer construction project on the city's south side, running along Alemany Boulevard, Boutwell Street, and Industrial Street. Owned by the SFPUC's Engineering Management Bureau, it involves building a new sewer system including a 5,650-foot, 10-foot-diameter tunnel, a 1,000-foot box sewer, and a 42-inch-diameter sewer. The project is currently active and in the design phase, with construction scheduled to run from January 2027 through June 2031. No cost figures have been published. | generated | 2026-07-17 | live |
| location.geometry | 5 geometries | reported | 2026-07-17 | live |
| location.street_limits | ALEMANY BLVD from STONEYBROOK AVE to HWY 101 S OFF RAMP; BOUTWELL ST; INDUSTRIAL ST from LOOMIS ST to BARNEVELD AVE | derived | 2026-07-17 | live |
| schedule.end | 2031-06-30 | reported | 2026-07-17 | live |
| schedule.start | 2027-01-02 | reported | 2026-07-17 | live |
| source.project_id | 8711 | reported | 2026-07-17 | live |
| agency.owner | SF PUC - Engineering Management Bureau | reported | 2026-07-17 | live |
| project_type | Combined | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | Construction of a new sewer that consists of 5,650 linear feet of 10-ft diameter tunnel, 1000 linear feet of 20 ft x 9-ft box sewer and 42-in diameter sewer. | reported | 2026-07-17 | live |
| name | Lower Alemany Area Stormwater Improvement Project | reported | 2026-07-17 | live |