SF Bay Ferry Downtown Ferry Terminal Electrification Project
candidate project
Design
6ae4baa8-abc0-4e74-8e48-8e006463474c
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF Bay Ferry |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF Bay Ferry” |
| contact.email | hank.phan@sfbayferry.com |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: hank.phan@sfbayferry.com” |
| contact.name | Hank Phan |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Hank Phan” |
| description | SF Bay Ferry (WETA) is proposing to bring 10MW from PG&E substation at Folsom & Fremont to Sea Wall Lot (SWL) 328 where the 34.5kV switchgear, stepdown transformer and 12.47kV switchgear will be installed. Power will then leave SWL 328 and run north along the Embarcadero to the Downtown SF Ferry Terminal where it will enter a transition vault to distribute to Gates E, F, and G. The project team is requesting utility and facility information for the following streets and sidewalks to identify conflicts. |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: SF Bay Ferry (WETA) is proposing to bring 10MW from PG&E substation at Folsom & Fremont to Sea Wall Lot (SWL) 328 where the 34.5kV switchgear,...” |
| location.geometry | 12 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“12 published segment geometries” |
| location.street_limits | BEALE ST from HARRISON ST to FOLSOM ST; FOLSOM ST from FREMONT ST to THE EMBARCADERO; FREMONT ST from FOLSOM ST to HARRISON ST; HARRISON ST from FREMONT ST to THE EMBARCADERO; HOWARD ST from SPEAR ST to THE EMBARCADERO; MAIN ST from HARRISON ST to FOLSOM ST; MISSION ST; SPEAR ST from END: 400-499 BLOCK to MISSION ST; STEUART ST from FOLSOM ST to DON CHEE WAY; THE EMBARCADERO from BRANNAN ST to MISSION ST; THE EMBARCADERO from HOWARD ST to HARRISON ST; THE EMBARCADERO from HOWARD ST to MISSION ST |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | SF Bay Ferry Downtown Ferry Terminal Electrification Project |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: SF Bay Ferry Downtown Ferry Terminal Electrification Project” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Electrical Distribution |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Electrical Distribution” |
| schedule.end | 2028-06-30 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2028-06-30T00:00:00.000” |
| schedule.start | 2024-04-01 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2024-04-01T00:00:00.000” |
| source.project_id | 55060 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 55060” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
Source records
| Public Works coordinated projects (DotMaps) | key 55060 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 12 geometries | reported | 2026-07-17 | live |
| location.street_limits | BEALE ST from HARRISON ST to FOLSOM ST; FOLSOM ST from FREMONT ST to THE EMBARCADERO; FREMONT ST from FOLSOM ST to HARRISON ST; HARRISON ST from FREMONT ST to THE EMBARCADERO; HOWARD ST from SPEAR ST to THE EMBARCADERO; MAIN ST from HARRISON ST to FOLSOM ST; MISSION ST; SPEAR ST from END: 400-499 BLOCK to MISSION ST; STEUART ST from FOLSOM ST to DON CHEE WAY; THE EMBARCADERO from BRANNAN ST to MISSION ST; THE EMBARCADERO from HOWARD ST to HARRISON ST; THE EMBARCADERO from HOWARD ST to MISSION ST | derived | 2026-07-17 | live |
| schedule.end | 2028-06-30 | reported | 2026-07-17 | live |
| schedule.start | 2024-04-01 | reported | 2026-07-17 | live |
| source.project_id | 55060 | reported | 2026-07-17 | live |
| contact.email | hank.phan@sfbayferry.com | reported | 2026-07-17 | live |
| contact.name | Hank Phan | reported | 2026-07-17 | live |
| agency.owner | SF Bay Ferry | reported | 2026-07-17 | live |
| project_type | Electrical Distribution | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | SF Bay Ferry (WETA) is proposing to bring 10MW from PG&E substation at Folsom & Fremont to Sea Wall Lot (SWL) 328 where the 34.5kV switchgear, stepdown transformer and 12.47kV switchgear will be installed. Power will then leave SWL 328 and run north along the Embarcadero to the Downtown SF Ferry Terminal where it will enter a transition vault to distribute to Gates E, F, and G. The project team is requesting utility and facility information for the following streets and sidewalks to identify conflicts. | reported | 2026-07-17 | live |
| name | SF Bay Ferry Downtown Ferry Terminal Electrification Project | reported | 2026-07-17 | live |