A gas infrastructure project led by PG&E, this active effort will replace or upgrade gas lines along Agua Way, Glenview Drive, and Sunview Drive in San Francisco's Miraloma Park area. The project is currently in the design phase, with construction scheduled to run from August 2026 to April 2027. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | PG&E - Gas (Capital Planning) |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: PG&E - Gas (Capital Planning)” |
| contact.email | s2d4@pge.com |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: s2d4@pge.com” |
| contact.name | Stephen Dupree |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Stephen Dupree” |
| location.geometry | 3 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“3 published segment geometries” |
| location.street_limits | AGUA WAY from CHAVES AVE to TERESITA BLVD; GLENVIEW DR from DAWNVIEW WAY to BURNETT AVE; SUNVIEW DR from PORTOLA DR to START: 1-99 BLOCK |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Sunview Dr |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Sunview Dr” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Gas |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Gas” |
| schedule.end | 2027-04-08 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2027-04-08T00:00:00.000” |
| schedule.start | 2026-08-10 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2026-08-10T00:00:00.000” |
| source.project_id | 8960 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 8960” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | A gas infrastructure project led by PG&E, this active effort will replace or upgrade gas lines along Agua Way,... |
generated
llm:summarize · retrieved 2026-07-17
“generated from 12 resolved fields; input sha256-v2=b789399f09d5274488b9cdf66ea0c56e8377c2b4f6c68ae59ce5cbf29379fccb” |
Source records
| Public Works coordinated projects (DotMaps) | key 8960 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| summary | A gas infrastructure project led by PG&E, this active effort will replace or upgrade gas lines along Agua Way, Glenview Drive, and Sunview Drive in San Francisco's Miraloma Park area. The project is currently in the design phase, with construction scheduled to run from August 2026 to April 2027. No cost figures have been published. | generated | 2026-07-17 | live |
| location.geometry | 3 geometries | reported | 2026-07-17 | live |
| location.street_limits | AGUA WAY from CHAVES AVE to TERESITA BLVD; GLENVIEW DR from DAWNVIEW WAY to BURNETT AVE; SUNVIEW DR from PORTOLA DR to START: 1-99 BLOCK | derived | 2026-07-17 | live |
| schedule.end | 2027-04-08 | reported | 2026-07-17 | live |
| schedule.start | 2026-08-10 | reported | 2026-07-17 | live |
| source.project_id | 8960 | reported | 2026-07-17 | live |
| contact.email | s2d4@pge.com | reported | 2026-07-17 | live |
| contact.name | Stephen Dupree | reported | 2026-07-17 | live |
| agency.owner | PG&E - Gas (Capital Planning) | reported | 2026-07-17 | live |
| project_type | Gas | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| name | Sunview Dr | reported | 2026-07-17 | live |