Various Locations Pavement Renovation Concrete No 93
candidate project
Planning
Pre-Planning
53bfece8-62a3-4fb7-9bf8-8f1b6807d7a9
A pavement renovation project managed by San Francisco Public Works, this effort will repave and reconstruct concrete roadways at more than two dozen locations across the city, including segments of Diamond Street, Juanita Way, Montgomery Street, and Scott Street. The project is in early pre-planning, with construction scheduled to run from February 2030 to May 2031. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Edmund.Lee@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Edmund.Lee@sfdpw.org” |
| contact.name | Edmund Lee |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Edmund Lee” |
| location.geometry | 27 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“27 published segment geometries” |
| location.street_limits | Acorn Aly from Leavenworth St to End; Castle St; Chestnut St from Stockton St to Powell St; Devonshire Way from Oak Park Dr to Crestmont Dr; Devonshire Way from Warren Dr to Oak Park Dr; Diamond St; Diamond St from Arbor St to Poppy Ln; Diamond St from Moreland St to Moffitt St; Diamond St from Poppy Ln to Sussex St; Hillway Ave from Carl St to Parnassus Ave; Juanita Way; Juanita Way from Lansdale Ave to Miraloma Dr; Juanita Way from Marne Ave to Lansdale Ave; Marne Ave from Miraloma Dr to Juanita Way; Melrose Ave from Congo St to Detroit St; Montgomery St; Montgomery St from Vallejo St to Green St; Scott St from Filbert St to Greenwich St; Scott St from Union St to Filbert St; Union St from Calhoun Ter to Montgomery St … |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Various Locations Pavement Renovation Concrete No 93 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Various Locations Pavement Renovation Concrete No 93” |
| phase | Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2031-05-13 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2031-05-13T00:00:00.000” |
| schedule.start | 2030-02-28 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2030-02-28T00:00:00.000” |
| source.project_id | 8982 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 8982” |
| status | Pre-Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Pre-Planning” |
| summary | A pavement renovation project managed by San Francisco Public Works, this effort will repave and reconstruct... |
generated
llm:summarize · retrieved 2026-07-17
“generated from 12 resolved fields; input sha256-v2=11d2d455f0b3ee87a1cd0ad85a45e5b84c7860667e3230d3ffcb636ee068637b” |
Source records
| Public Works coordinated projects (DotMaps) | key 8982 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| summary | A pavement renovation project managed by San Francisco Public Works, this effort will repave and reconstruct concrete roadways at more than two dozen locations across the city, including segments of Diamond Street, Juanita Way, Montgomery Street, and Scott Street. The project is in early pre-planning, with construction scheduled to run from February 2030 to May 2031. No cost figures have been published. | generated | 2026-07-17 | live |
| location.geometry | 27 geometries | reported | 2026-07-17 | live |
| location.street_limits | Acorn Aly from Leavenworth St to End; Castle St; Chestnut St from Stockton St to Powell St; Devonshire Way from Oak Park Dr to Crestmont Dr; Devonshire Way from Warren Dr to Oak Park Dr; Diamond St; Diamond St from Arbor St to Poppy Ln; Diamond St from Moreland St to Moffitt St; Diamond St from Poppy Ln to Sussex St; Hillway Ave from Carl St to Parnassus Ave; Juanita Way; Juanita Way from Lansdale Ave to Miraloma Dr; Juanita Way from Marne Ave to Lansdale Ave; Marne Ave from Miraloma Dr to Juanita Way; Melrose Ave from Congo St to Detroit St; Montgomery St; Montgomery St from Vallejo St to Green St; Scott St from Filbert St to Greenwich St; Scott St from Union St to Filbert St; Union St from Calhoun Ter to Montgomery St … | derived | 2026-07-17 | live |
| schedule.end | 2031-05-13 | reported | 2026-07-17 | live |
| schedule.start | 2030-02-28 | reported | 2026-07-17 | live |
| source.project_id | 8982 | reported | 2026-07-17 | live |
| contact.email | Edmund.Lee@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Edmund Lee | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | live |
| status | Pre-Planning | reported | 2026-07-17 | live |
| name | Various Locations Pavement Renovation Concrete No 93 | reported | 2026-07-17 | live |