Muni Facility Upgrades — Transportation and Road Improvement GO Bond (2014)

funding source 4f1b3f08-0eeb-411e-b71b-61e92a0334ce

Muni Facility Upgrades is a funding source within San Francisco's Transportation and Road Improvement general obligation bond program, approved by voters on November 4, 2014, to pay for upgrades to Muni transit facilities. Of the roughly $67.7 million originally authorized, about $84.6 million has been issued and about $76.7 million spent—roughly 113% of the authorized amount—with about $6.2 million remaining. The work is well behind its original timeline, now projected to finish in May 2029 rather than the end of 2022, about six years late.AI-generated

Current record

FieldValueProvenance
funding.authorized $67,722,343 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“bondauthamount: 67722343 (fiscal_year FY24-25)”
funding.encumbered $1,671,087 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“encumbrance: 1671087.17 (fiscal_year FY24-25)”
funding.expended $76,692,421 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“expended: 76692421.315 (fiscal_year FY24-25)”
funding.issued $84,609,881 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“issuedtodate: 84609881.1 (fiscal_year FY24-25)”
funding.measure_year 2014 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“year: 2014”
funding.program Transportation and Road Improvement reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“bondprogram: Transportation and Road Improvement”
funding.remaining $6,246,373 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“remaining_balance: 6246373 (fiscal_year FY24-25)”
funding.revised_budget $84,609,881 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“revisedbudget: 84609881.1 (fiscal_year FY24-25)”
funding.voter_approved 2014-11-04 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“voter_approved_date: 2014-11-04T00:00:00.000”
name Muni Facility Upgrades — Transportation and Road Improvement GO Bond (2014) derived socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“bondprogram: Transportation and Road Improvement; year: 2014; component_programitem: Muni Facility Upgrades”
schedule.end_original 2022-12-31 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“originalenddate: 2022-12-31T00:00:00.000”
schedule.end_projected 2029-05-03 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“projectedenddate: 2029-05-03T00:00:00.000”
summary Muni Facility Upgrades is a funding source within San Francisco's Transportation and Road Improvement general... generated llm:summarize · retrieved 2026-07-29
“generated from 12 resolved fields; input sha256-v2=83fe70ad7f5525ac4a496bc998126fb418b62b59e95bd902352a36dac939ca6d”

Source records

General Obligation Bond program spending and status key 2014|Transportation and Road Improvement|Muni Facility Upgrades primary · rule:gobonds-group-by-program-year-component dataset page ↗ · this record’s data ↗

Assertion history (latest 100, including superseded)

PredicateValueClassRecordedState
summary Muni Facility Upgrades is a funding source within San Francisco's Transportation and Road Improvement general obligation bond program, approved by voters on November 4, 2014, to pay for upgrades to Muni transit facilities. Of the roughly $67.7 million originally authorized, about $84.6 million has been issued and about $76.7 million spent—roughly 113% of the authorized amount—with about $6.2 million remaining. The work is well behind its original timeline, now projected to finish in May 2029 rather than the end of 2022, about six years late. generated 2026-07-29 live
funding.voter_approved 2014-11-04 reported 2026-07-29 live
schedule.end_projected 2029-05-03 reported 2026-07-29 live
schedule.end_original 2022-12-31 reported 2026-07-29 live
funding.remaining $6,246,373 reported 2026-07-29 live
funding.encumbered $1,671,087 reported 2026-07-29 live
funding.expended $76,692,421 reported 2026-07-29 live
funding.issued $84,609,881 reported 2026-07-29 live
funding.revised_budget $84,609,881 reported 2026-07-29 live
funding.authorized $67,722,343 reported 2026-07-29 live
funding.measure_year 2014 reported 2026-07-29 live
funding.program Transportation and Road Improvement reported 2026-07-29 live
name Muni Facility Upgrades — Transportation and Road Improvement GO Bond (2014) derived 2026-07-29 live