Brotherhood Way Pavement Renovation
candidate project
Planning
Pre-Planning
418da199-84e4-44de-9b57-31e5effb543b
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Ramon.Kong@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Ramon.Kong@sfdpw.org” |
| contact.name | Ramon Kong |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Ramon Kong” |
| location.geometry | 21 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“21 published segment geometries” |
| location.street_limits | Arch St; Brotherhood Way; Brotherhood Way from Alemany Blvd \ Sagamore St to Arch St; Brotherhood Way from Alemany Blvd to Arch St; Brotherhood Way from Arch St to Junipero Serra Blvd On Ramp; Brotherhood Way from Church Access Rd to Church Access Rd; Brotherhood Way from Church Access Rd to Lake Merced Blvd; Brotherhood Way from Junipero Serra Blvd On Ramp to Junipero Serra Blvd Off Ramp; Brotherhood Way from Summit Way to Church Access Rd |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Brotherhood Way Pavement Renovation |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Brotherhood Way Pavement Renovation” |
| phase | Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2035-10-01 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2035-10-01T00:00:00.000” |
| schedule.start | 2034-07-19 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2034-07-19T00:00:00.000” |
| source.project_id | 17352 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 17352” |
| status | Pre-Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Pre-Planning” |
Source records
| Public Works coordinated projects (DotMaps) | key 17352 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 21 geometries | reported | 2026-07-17 | live |
| location.street_limits | Arch St; Brotherhood Way; Brotherhood Way from Alemany Blvd \ Sagamore St to Arch St; Brotherhood Way from Alemany Blvd to Arch St; Brotherhood Way from Arch St to Junipero Serra Blvd On Ramp; Brotherhood Way from Church Access Rd to Church Access Rd; Brotherhood Way from Church Access Rd to Lake Merced Blvd; Brotherhood Way from Junipero Serra Blvd On Ramp to Junipero Serra Blvd Off Ramp; Brotherhood Way from Summit Way to Church Access Rd | derived | 2026-07-17 | live |
| schedule.end | 2035-10-01 | reported | 2026-07-17 | live |
| schedule.start | 2034-07-19 | reported | 2026-07-17 | live |
| source.project_id | 17352 | reported | 2026-07-17 | live |
| contact.email | Ramon.Kong@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Ramon Kong | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | live |
| status | Pre-Planning | reported | 2026-07-17 | live |
| name | Brotherhood Way Pavement Renovation | reported | 2026-07-17 | live |