MTA 4th St and I 80 Vision Zero Improvements
candidate project
Construction
41463a65-f6ce-4b57-bfdc-98f20980346c
This is a roadway safety project along 4th Street near the I-80 interchange in San Francisco's South of Market area, including sidewalk bulb-outs at 4th and Harrison and 4th and Bryant. Part of the city's Vision Zero effort to reduce traffic injuries, the work is owned by San Francisco Public Works' Streets & Highways division and is currently in construction, which began in February 2025 and is scheduled to finish in November 2026. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Ellen.Wong@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“project_manager_email: Ellen.Wong@sfdpw.org” |
| contact.name | Ellen Wong |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“project_manager_name: Ellen Wong” |
| description | Design bulbs at 4th st and Harrison amd Byrant and 4th st |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“description: Design bulbs at 4th st and Harrison amd Byrant and 4th st” |
| location.geometry | 12 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“12 published segment geometries” |
| location.street_limits | 04th St; 04th St from Bryant St \ I-80 E Off Ramp to Welsh St; 04th St from Clara St to Harrison St \ I-80 W On Ramp; 04th St from Harrison St \ I-80 W On Ramp to Perry St; 04th St from Perry St to Stillman St; 04th St from Stillman St to Bryant St \ I-80 E Off Ramp; Bryant St from 04th St \ I-80 E Off Ramp to 05th St \ I-80 E On Ramp; Harrison St from 04th St \ I-80 W On Ramp to 05th St \ I-80 W Off Ramp; Harrison St from Lapu-Lapu St to 04th St \ I-80 W On Ramp |
derived
socrata:btxj-k9uh · retrieved 2026-08-11
“assembled from segment on/from/to street fields” |
| name | MTA 4th St and I 80 Vision Zero Improvements |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“name: MTA 4th St and I 80 Vision Zero Improvements” |
| phase | Construction |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“project_phase: Construction” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“facility_type: Roadway” |
| schedule.end | 2026-11-20 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“end_date: 2026-11-20T00:00:00.000” |
| schedule.start | 2025-02-24 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“start_date: 2025-02-24T00:00:00.000” |
| source.project_id | 7997 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“dotmapsid: 7997” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“project_status: Active” |
| summary | This is a roadway safety project along 4th Street near the I-80 interchange in San Francisco's South of Market area,... |
generated
llm:summarize · retrieved 2026-08-11
“generated from 13 resolved fields; input sha256-v2=84715924ea94f3e82e875926320e093de690ac97882026772d9308b6a05427b9” |
Changes
| 2026-08-27 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 7997 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 12 geometries | reported | 2026-08-27 | live |
| summary | This is a roadway safety project along 4th Street near the I-80 interchange in San Francisco's South of Market area, including sidewalk bulb-outs at 4th and Harrison and 4th and Bryant. Part of the city's Vision Zero effort to reduce traffic injuries, the work is owned by San Francisco Public Works' Streets & Highways division and is currently in construction, which began in February 2025 and is scheduled to finish in November 2026. No cost figures have been published. | generated | 2026-08-11 | live |
| location.geometry | 12 geometries | reported | 2026-08-11 | superseded |
| location.street_limits | 04th St; 04th St from Bryant St \ I-80 E Off Ramp to Welsh St; 04th St from Clara St to Harrison St \ I-80 W On Ramp; 04th St from Harrison St \ I-80 W On Ramp to Perry St; 04th St from Perry St to Stillman St; 04th St from Stillman St to Bryant St \ I-80 E Off Ramp; Bryant St from 04th St \ I-80 E Off Ramp to 05th St \ I-80 E On Ramp; Harrison St from 04th St \ I-80 W On Ramp to 05th St \ I-80 W Off Ramp; Harrison St from Lapu-Lapu St to 04th St \ I-80 W On Ramp | derived | 2026-08-11 | live |
| schedule.end | 2026-11-20 | reported | 2026-08-11 | live |
| schedule.start | 2025-02-24 | reported | 2026-08-11 | live |
| source.project_id | 7997 | reported | 2026-08-11 | live |
| contact.email | Ellen.Wong@sfdpw.org | reported | 2026-08-11 | live |
| contact.name | Ellen Wong | reported | 2026-08-11 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-08-11 | live |
| project_type | Roadway | reported | 2026-08-11 | live |
| phase | Construction | reported | 2026-08-11 | live |
| status | Active | reported | 2026-08-11 | live |
| description | Design bulbs at 4th st and Harrison amd Byrant and 4th st | reported | 2026-08-11 | live |
| name | MTA 4th St and I 80 Vision Zero Improvements | reported | 2026-08-11 | live |