R3 G 50A DIMP UP STEINER & VALLEJO, SF
candidate project
Planning
2792aae8-3f34-479c-aebe-795543230a26
A PG&E gas distribution project in San Francisco's Pacific Heights and Cow Hollow area, this effort would replace or upgrade gas mains along portions of Steiner, Vallejo, Pierce, and Green streets. Owned by PG&E's Gas Capital Planning group, the project is currently in the planning phase and listed as active, with construction scheduled to run through 2026. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | PG&E - Gas (Capital Planning) |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: PG&E - Gas (Capital Planning)” |
| location.geometry | 4 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“4 published segment geometries” |
| location.street_limits | GREEN ST; PIERCE ST from GREEN ST to VALLEJO ST; STEINER ST from GREEN ST to VALLEJO ST; VALLEJO ST from SCOTT ST to PIERCE ST |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | R3 G 50A DIMP UP STEINER & VALLEJO, SF |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: R3 G 50A DIMP UP STEINER & VALLEJO, SF” |
| phase | Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning” |
| project_type | Gas Distribution |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Gas Distribution” |
| schedule.end | 2026-12-31 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2026-12-31T00:00:00.000” |
| schedule.start | 2026-01-01 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2026-01-01T00:00:00.000” |
| source.project_id | 10169 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 10169” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | A PG&E gas distribution project in San Francisco's Pacific Heights and Cow Hollow area, this effort would replace or... |
generated
llm:summarize · retrieved 2026-07-18
“generated from 10 resolved fields; input sha256-v2=f8df07a4aa02ccf576431d82fa2b8f4ae28af7258f1f1933f060cb103e2c4cca” |
Changes
| 2026-08-27 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 10169 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 4 geometries | reported | 2026-08-27 | live |
| summary | A PG&E gas distribution project in San Francisco's Pacific Heights and Cow Hollow area, this effort would replace or upgrade gas mains along portions of Steiner, Vallejo, Pierce, and Green streets. Owned by PG&E's Gas Capital Planning group, the project is currently in the planning phase and listed as active, with construction scheduled to run through 2026. No cost figures have been published. | generated | 2026-07-18 | live |
| location.geometry | 4 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | GREEN ST; PIERCE ST from GREEN ST to VALLEJO ST; STEINER ST from GREEN ST to VALLEJO ST; VALLEJO ST from SCOTT ST to PIERCE ST | derived | 2026-07-17 | live |
| schedule.end | 2026-12-31 | reported | 2026-07-17 | live |
| schedule.start | 2026-01-01 | reported | 2026-07-17 | live |
| source.project_id | 10169 | reported | 2026-07-17 | live |
| agency.owner | PG&E - Gas (Capital Planning) | reported | 2026-07-17 | live |
| project_type | Gas Distribution | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| name | R3 G 50A DIMP UP STEINER & VALLEJO, SF | reported | 2026-07-17 | live |