Cesar Chavez St from Hampshire St to Guerrero St Pavement Renovation
candidate project
Planning
Pre-Planning
25467f30-619b-4c84-926d-ddcc31e6906c
This is a planned pavement renovation of Cesar Chavez Street in San Francisco, stretching roughly from Hampshire Street to Guerrero Street across the Mission District, owned by San Francisco Public Works (Streets & Highways). The roadway project covers 34 street segments and is currently in the pre-planning/planning phase, with construction scheduled to run from late 2031 to early 2033. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Streets & Highways |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Streets & Highways” |
| contact.email | Therese.Topacio@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Therese.Topacio@sfdpw.org” |
| contact.name | Therese Topacio |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Therese Topacio” |
| location.geometry | 34 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“34 published segment geometries” |
| location.street_limits | Cesar Chavez St; Cesar Chavez St from Alabama St to Harrison St; Cesar Chavez St from Bartlett St to Valencia St; Cesar Chavez St from Bryant St to Florida St; Cesar Chavez St from Capp St \ Mission St to Bartlett St; Cesar Chavez St from Capp St \ Mission St to Valencia St; Cesar Chavez St from Cesar Chavez On Ramp \ Hampshire St to Precita Ave \ York St; Cesar Chavez St from End to Guerrero St; Cesar Chavez St from Florida St to Alabama St; Cesar Chavez St from Folsom St to Shotwell St; Cesar Chavez St from Harrison St to Folsom St; Cesar Chavez St from Hwy 101 S On Ramp to Cesar Chavez On Ramp \ Hampshire St; Cesar Chavez St from Precita Ave \ York St to Bryant St; Cesar Chavez St from Shotwell St to South Van Ness Ave; Cesar Chavez St from South Van Ness Ave to Capp St \ Mission St; Cesar Chavez St from Valencia St to End; Cesar Chavez St from Valencia St to Guerrero St |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Cesar Chavez St from Hampshire St to Guerrero St Pavement Renovation |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Cesar Chavez St from Hampshire St to Guerrero St Pavement Renovation” |
| phase | Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2033-03-13 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2033-03-13T00:00:00.000” |
| schedule.start | 2031-12-29 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2031-12-29T00:00:00.000” |
| source.project_id | 56593 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 56593” |
| status | Pre-Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Pre-Planning” |
| summary | This is a planned pavement renovation of Cesar Chavez Street in San Francisco, stretching roughly from Hampshire... |
generated
llm:summarize · retrieved 2026-07-18
“generated from 12 resolved fields; input sha256-v2=a716d425073b72e3dcb22548b1f5ffe534f3f1e26b1e4895f08da9bf4b7bfe85” |
Changes
| 2026-08-27 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 56593 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 34 geometries | reported | 2026-08-27 | live |
| summary | This is a planned pavement renovation of Cesar Chavez Street in San Francisco, stretching roughly from Hampshire Street to Guerrero Street across the Mission District, owned by San Francisco Public Works (Streets & Highways). The roadway project covers 34 street segments and is currently in the pre-planning/planning phase, with construction scheduled to run from late 2031 to early 2033. No cost figures have been published. | generated | 2026-07-18 | live |
| location.geometry | 34 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | Cesar Chavez St; Cesar Chavez St from Alabama St to Harrison St; Cesar Chavez St from Bartlett St to Valencia St; Cesar Chavez St from Bryant St to Florida St; Cesar Chavez St from Capp St \ Mission St to Bartlett St; Cesar Chavez St from Capp St \ Mission St to Valencia St; Cesar Chavez St from Cesar Chavez On Ramp \ Hampshire St to Precita Ave \ York St; Cesar Chavez St from End to Guerrero St; Cesar Chavez St from Florida St to Alabama St; Cesar Chavez St from Folsom St to Shotwell St; Cesar Chavez St from Harrison St to Folsom St; Cesar Chavez St from Hwy 101 S On Ramp to Cesar Chavez On Ramp \ Hampshire St; Cesar Chavez St from Precita Ave \ York St to Bryant St; Cesar Chavez St from Shotwell St to South Van Ness Ave; Cesar Chavez St from South Van Ness Ave to Capp St \ Mission St; Cesar Chavez St from Valencia St to End; Cesar Chavez St from Valencia St to Guerrero St | derived | 2026-07-17 | live |
| schedule.end | 2033-03-13 | reported | 2026-07-17 | live |
| schedule.start | 2031-12-29 | reported | 2026-07-17 | live |
| source.project_id | 56593 | reported | 2026-07-17 | live |
| contact.email | Therese.Topacio@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Therese Topacio | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Streets & Highways | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | live |
| status | Pre-Planning | reported | 2026-07-17 | live |
| name | Cesar Chavez St from Hampshire St to Guerrero St Pavement Renovation | reported | 2026-07-17 | live |