sfproj. every fact links to its evidence

← all projects

8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement (JV w 8th St, Clay St and Leavenworth St Pavement Renovation)

candidate project Construction 1b1fc6f5-7ddd-4cea-8e1a-119d65cb7c56

The 8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement is an active sanitary sewer project managed by San Francisco Public Works. Carried out jointly with pavement renovation work on 8th, Clay and Leavenworth streets, it replaces sewer lines across roughly two dozen street segments in the SoMa and Nob Hill/Tenderloin areas. Construction began in February 2025 and is scheduled to finish in October 2026. No cost figures have been published.AI-generated

Current record

FieldValueProvenance
agency.owner SF DPW IDC - Hydraulic reported socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Hydraulic”
contact.email Lesley.Wong@sfdpw.org reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Lesley.Wong@sfdpw.org”
contact.name Lesley Wong reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Lesley Wong”
location.geometry 23 geometries reported socrata:btxj-k9uh · retrieved 2026-08-27
“23 published segment geometries”
location.street_limits 07th St; 08th St; 08th St from Grove St \ Hyde St \ Market St to Stevenson St; 08th St from Howard St to Tehama St; 08th St from Minna St to Natoma St; 08th St from Mission St to Minna St; 08th St from Natoma St to Howard St; 08th St from Stevenson St to Mission St; Clay St; Clay St from Hyde St to Torrens Ct; Clay St from Jones St to Leavenworth St; Clay St from Larkin St to Polk St; Clay St from Torrens Ct to Larkin St; Larkin St; Larkin St from Sacramento St to Clay St; Larkin St from Washington St to Jackson St; Leavenworth St from Golden Gate Ave to Turk St derived socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields”
name 8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement (JV w 8th St, Clay St and Leavenworth St Pavement Renovation) reported socrata:btxj-k9uh · retrieved 2026-07-17
“name: 8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement (JV w 8th St, Clay St and Leavenworth St Pavement Renovation)”
phase Construction reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Construction”
project_type Sanitary Sewer reported socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Sanitary Sewer”
schedule.end 2026-10-27 reported socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2026-10-27T00:00:00.000”
schedule.start 2025-02-03 reported socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2025-02-03T00:00:00.000”
source.project_id 25813 reported socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 25813”
status Active reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active”
summary The 8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement is an active sanitary sewer project managed by... generated llm:summarize · retrieved 2026-07-18
“generated from 12 resolved fields; input sha256-v2=a48e8708d0c1b0b22ab1db16ea322fa0715cb384f498d4f7d9cc1c23a836698c”

Changes

2026-08-27 field changed immaterial {'type': 'GeometryCollection', 'geometries': [{'type': 'Point', 'coordinates': [-122.41215795394407, 37.776660987170835]}, {'type': 'Point', 'coordinates': [-122.41261666678729, 37.77702642031894]}, {'type': 'Point', 'coordinates': [-122.41315769117062, 37.77745741982889]}, {'type': 'Point', 'coordinates': [-122.41414337572311, 37.77824088372332]}, {'type': 'Point', 'coordinates': [-122.41474122154682, 37.77871942930068]}, {'type': 'Point', 'coordinates': [-122.41447007452219, 37.79322314637016]}, {'type': 'Point', 'coordinates': [-122.4161130164544, 37.79301360839089]}, {'type': 'Point', 'coordinates': [-122.41922173687273, 37.791704015511684]}, {'type': 'Point', 'coordinates': [-122.41940178390682, 37.792593083069214]}, {'type': 'Point', 'coordinates': [-122.4125122557686, 37.78047851233428]}, {'type': 'LineString', 'coordinates': [[-122.41474122182065, 37.77871942923136], [-122.41414337555413, 37.778240883661205]]}, {'type': 'LineString', 'coordinates': [[-122.41414337555413, 37.778240883661205], [-122.41315769144896, 37.77745741993531]]}, {'type': 'LineString', 'coordinates': [[-122.41315769144896, 37.77745741993531], [-122.41261666662284, 37.777026420432556]]}, {'type': 'LineString', 'coordinates': [[-122.41261666662284, 37.777026420432556], [-122.4121579537751, 37.776660987108706]]}, {'type': 'LineString', 'coordinates': [[-122.4121579537751, 37.776660987108706], [-122.411606112841, 37.77622135611429]]}, {'type': 'LineString', 'coordinates': [[-122.411606112841, 37.77622135611429], [-122.4110694425639, 37.77579380428469]]}, {'type': 'LineString', 'coordinates': [[-122.41447007457462, 37.793223146304456], [-122.4161130162899, 37.79301360850451]]}, {'type': 'LineString', 'coordinates': [[-122.41775911821975, 37.792803643249464], [-122.41857675509638, 37.79269883989393]]}, {'type': 'LineString', 'coordinates': [[-122.41857675509638, 37.79269883989393], [-122.41940178396379, 37.79259308317921]]}, {'type': 'LineString', 'coordinates': [[-122.41940178396379, 37.79259308317921], [-122.42105287423561, 37.792383253429755]]}, {'type': 'LineString', 'coordinates': [[-122.4192217366992, 37.79170401527384], [-122.41940178396379, 37.79259308317921]]}, {'type': 'LineString', 'coordinates': [[-122.41957912340112, 37.793466928519884], [-122.41975272026752, 37.794353779458596]]}, {'type': 'LineString', 'coordinates': [[-122.41386560359761, 37.78186333951648], [-122.41405376489428, 37.78279444630632]]}]}{'type': 'GeometryCollection', 'geometries': [{'type': 'Point', 'coordinates': [-122.41215795, 37.77666099]}, {'type': 'Point', 'coordinates': [-122.41261667, 37.77702642]}, {'type': 'Point', 'coordinates': [-122.41315769, 37.77745742]}, {'type': 'Point', 'coordinates': [-122.41414338, 37.77824088]}, {'type': 'Point', 'coordinates': [-122.41474122, 37.77871943]}, {'type': 'Point', 'coordinates': [-122.41447007, 37.79322315]}, {'type': 'Point', 'coordinates': [-122.41611302, 37.79301361]}, {'type': 'Point', 'coordinates': [-122.41922174, 37.79170402]}, {'type': 'Point', 'coordinates': [-122.41940178, 37.79259308]}, {'type': 'Point', 'coordinates': [-122.41251226, 37.78047851]}, {'type': 'LineString', 'coordinates': [[-122.41474122, 37.77871943], [-122.41414338, 37.77824088]]}, {'type': 'LineString', 'coordinates': [[-122.41414338, 37.77824088], [-122.41315769, 37.77745742]]}, {'type': 'LineString', 'coordinates': [[-122.41315769, 37.77745742], [-122.41261667, 37.77702642]]}, {'type': 'LineString', 'coordinates': [[-122.41261667, 37.77702642], [-122.41215795, 37.77666099]]}, {'type': 'LineString', 'coordinates': [[-122.41215795, 37.77666099], [-122.41160611, 37.77622136]]}, {'type': 'LineString', 'coordinates': [[-122.41160611, 37.77622136], [-122.41106944, 37.7757938]]}, {'type': 'LineString', 'coordinates': [[-122.41447007, 37.79322315], [-122.41611302, 37.79301361]]}, {'type': 'LineString', 'coordinates': [[-122.41775912, 37.79280364], [-122.41857676, 37.79269884]]}, {'type': 'LineString', 'coordinates': [[-122.41857676, 37.79269884], [-122.41940178, 37.79259308]]}, {'type': 'LineString', 'coordinates': [[-122.41940178, 37.79259308], [-122.42105287, 37.79238325]]}, {'type': 'LineString', 'coordinates': [[-122.41922174, 37.79170402], [-122.41940178, 37.79259308]]}, {'type': 'LineString', 'coordinates': [[-122.41957912, 37.79346693], [-122.41975272, 37.79435378]]}, {'type': 'LineString', 'coordinates': [[-122.4138656, 37.78186334], [-122.41405376, 37.78279445]]}]}

Source records

Public Works coordinated projects (DotMaps) key 25813 primary · rule:dotmaps-group-by-dotmapsid dataset page ↗ · this record’s data ↗

Assertion history (latest 100, including superseded)

PredicateValueClassRecordedState
location.geometry 23 geometries reported 2026-08-27 live
summary The 8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement is an active sanitary sewer project managed by San Francisco Public Works. Carried out jointly with pavement renovation work on 8th, Clay and Leavenworth streets, it replaces sewer lines across roughly two dozen street segments in the SoMa and Nob Hill/Tenderloin areas. Construction began in February 2025 and is scheduled to finish in October 2026. No cost figures have been published. generated 2026-07-18 live
location.geometry 23 geometries reported 2026-07-17 superseded
location.street_limits 07th St; 08th St; 08th St from Grove St \ Hyde St \ Market St to Stevenson St; 08th St from Howard St to Tehama St; 08th St from Minna St to Natoma St; 08th St from Mission St to Minna St; 08th St from Natoma St to Howard St; 08th St from Stevenson St to Mission St; Clay St; Clay St from Hyde St to Torrens Ct; Clay St from Jones St to Leavenworth St; Clay St from Larkin St to Polk St; Clay St from Torrens Ct to Larkin St; Larkin St; Larkin St from Sacramento St to Clay St; Larkin St from Washington St to Jackson St; Leavenworth St from Golden Gate Ave to Turk St derived 2026-07-17 live
schedule.end 2026-10-27 reported 2026-07-17 live
schedule.start 2025-02-03 reported 2026-07-17 live
source.project_id 25813 reported 2026-07-17 live
contact.email Lesley.Wong@sfdpw.org reported 2026-07-17 live
contact.name Lesley Wong reported 2026-07-17 live
agency.owner SF DPW IDC - Hydraulic reported 2026-07-17 live
project_type Sanitary Sewer reported 2026-07-17 live
phase Construction reported 2026-07-17 live
status Active reported 2026-07-17 live
name 8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement (JV w 8th St, Clay St and Leavenworth St Pavement Renovation) reported 2026-07-17 live