1415-011: 8-inch Ductile Iron Water Main Replacement on 22nd Street from Castro to Church Streets, on Noe Street from 20th to Alvarado Streets and Various Side Streets
candidate project
Planning
Pre-Planning
11d70505-ab1c-4852-a5fc-cc171777c19a
This is a San Francisco Public Utilities Commission water project to replace aging 8-inch ductile iron water mains in the Noe Valley area, primarily along 22nd Street from Castro to Church Streets, Noe Street from 20th to Alvarado Streets, and several adjacent side streets. The project is in pre-planning, with construction scheduled to run from February 2026 to March 2028. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF PUC Water |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF PUC Water” |
| description | None8-inch Ductile Iron Water Main Replacement on 22nd Street from Castro to Church Streets, on Noe Street from 20th to Alvarado Streets and Various Side Streets |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: None8-inch Ductile Iron Water Main Replacement on 22nd Street from Castro to Church Streets, on Noe Street from 20th to Alvarado Streets and...” |
| location.geometry | 8 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“8 published segment geometries” |
| location.street_limits | 20TH ST; 20TH ST from 20TH ST to NOE ST; 20TH ST from COLLINGWOOD ST to NOE ST; 22ND ST from CASTRO ST to CHURCH ST; ALVARADO ST from CASTRO ST to SANCHEZ ST; LIBERTY ST; NOE ST; SANCHEZ ST from 20TH ST to ALVARADO ST |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | 1415-011: 8-inch Ductile Iron Water Main Replacement on 22nd Street from Castro to Church Streets, on Noe Street from 20th to Alvarado Streets and Various Side Streets |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: 1415-011: 8-inch Ductile Iron Water Main Replacement on 22nd Street from Castro to Church Streets, on Noe Street from 20th to Alvarado Streets and...” |
| phase | Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning” |
| project_type | Water |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Water” |
| schedule.end | 2028-03-30 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2028-03-30T00:00:00.000” |
| schedule.start | 2026-02-01 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2026-02-01T00:00:00.000” |
| source.project_id | 8748 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 8748” |
| status | Pre-Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Pre-Planning” |
| summary | This is a San Francisco Public Utilities Commission water project to replace aging 8-inch ductile iron water mains... |
generated
llm:summarize · retrieved 2026-07-17
“generated from 11 resolved fields; input sha256-v2=4fb0e4eeb8183e94a83b6be93978a9fd1fa74427f1ea90b5c77b394c97181c51” |
Source records
| Public Works coordinated projects (DotMaps) | key 8748 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| summary | This is a San Francisco Public Utilities Commission water project to replace aging 8-inch ductile iron water mains in the Noe Valley area, primarily along 22nd Street from Castro to Church Streets, Noe Street from 20th to Alvarado Streets, and several adjacent side streets. The project is in pre-planning, with construction scheduled to run from February 2026 to March 2028. No cost figures have been published. | generated | 2026-07-17 | live |
| location.geometry | 8 geometries | reported | 2026-07-17 | live |
| location.street_limits | 20TH ST; 20TH ST from 20TH ST to NOE ST; 20TH ST from COLLINGWOOD ST to NOE ST; 22ND ST from CASTRO ST to CHURCH ST; ALVARADO ST from CASTRO ST to SANCHEZ ST; LIBERTY ST; NOE ST; SANCHEZ ST from 20TH ST to ALVARADO ST | derived | 2026-07-17 | live |
| schedule.end | 2028-03-30 | reported | 2026-07-17 | live |
| schedule.start | 2026-02-01 | reported | 2026-07-17 | live |
| source.project_id | 8748 | reported | 2026-07-17 | live |
| agency.owner | SF PUC Water | reported | 2026-07-17 | live |
| project_type | Water | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | live |
| status | Pre-Planning | reported | 2026-07-17 | live |
| description | None8-inch Ductile Iron Water Main Replacement on 22nd Street from Castro to Church Streets, on Noe Street from 20th to Alvarado Streets and Various Side Streets | reported | 2026-07-17 | live |
| name | 1415-011: 8-inch Ductile Iron Water Main Replacement on 22nd Street from Castro to Church Streets, on Noe Street from 20th to Alvarado Streets and Various Side Streets | reported | 2026-07-17 | live |