PW Various Locations Sewer Replacement (JV VL PR No 78)
candidate project
Design
1148db58-65ea-4bfb-a7a9-ff86d9b6c9bf
This is a sanitary sewer replacement project owned by San Francisco Public Works (Hydraulic division) that will rebuild aging sewer lines at various locations across the city, including stretches of Oak Street, Grove Street, and 34th Avenue, among others. The project is currently active and in the design phase, with construction scheduled to run from March 2026 to June 2027. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF DPW IDC - Hydraulic |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF DPW IDC - Hydraulic” |
| contact.email | Lesley.Wong@sfdpw.org |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: Lesley.Wong@sfdpw.org” |
| contact.name | Lesley Wong |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Lesley Wong” |
| description | 2350i |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: 2350i” |
| location.geometry | 9 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“9 published segment geometries” |
| location.street_limits | 34th Ave from Geary Blvd to Anza St; Ashbury St; Buchanan St from Duboce Ave \ Market St to Hermann St; Cole St; Grove St from Ashbury St to Clayton St; Oak St; Oak St from Fillmore St to Steiner St |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | PW Various Locations Sewer Replacement (JV VL PR No 78) |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: PW Various Locations Sewer Replacement (JV VL PR No 78)” |
| phase | Design |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design” |
| project_type | Sanitary Sewer |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Sanitary Sewer” |
| schedule.end | 2027-06-12 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“end_date: 2027-06-12T00:00:00.000” |
| schedule.start | 2026-03-30 |
reported
socrata:btxj-k9uh · retrieved 2026-08-11
“start_date: 2026-03-30T00:00:00.000” |
| source.project_id | 26063 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 26063” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | This is a sanitary sewer replacement project owned by San Francisco Public Works (Hydraulic division) that will... |
generated
llm:summarize · retrieved 2026-08-11
“generated from 13 resolved fields; input sha256-v2=cac0fbccf38344f8f0f655a3c2b732e20979b46dab1a3fd65c20b2b18f21bc5d” |
Changes
| 2026-08-27 | field changed immaterial | |
| 2026-08-11 | completion date changed immaterial | |
| 2026-08-11 | start date changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 26063 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 9 geometries | reported | 2026-08-27 | live |
| summary | This is a sanitary sewer replacement project owned by San Francisco Public Works (Hydraulic division) that will rebuild aging sewer lines at various locations across the city, including stretches of Oak Street, Grove Street, and 34th Avenue, among others. The project is currently active and in the design phase, with construction scheduled to run from March 2026 to June 2027. No cost figures have been published. | generated | 2026-08-11 | live |
| schedule.end | 2027-06-12 | reported | 2026-08-11 | live |
| schedule.start | 2026-03-30 | reported | 2026-08-11 | live |
| summary | This is a sanitary sewer replacement project owned by San Francisco Public Works (Hydraulic division) that will replace sewer lines at various locations across the city, including stretches of 34th Avenue, Buchanan Street, Grove Street, and Oak Street. The project is currently in the design phase, with construction scheduled to run from March 2026 to June 2027. No cost figures have been published. | generated | 2026-07-18 | superseded |
| location.geometry | 9 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | 34th Ave from Geary Blvd to Anza St; Ashbury St; Buchanan St from Duboce Ave \ Market St to Hermann St; Cole St; Grove St from Ashbury St to Clayton St; Oak St; Oak St from Fillmore St to Steiner St | derived | 2026-07-17 | live |
| schedule.end | 2027-06-04 | reported | 2026-07-17 | superseded |
| schedule.start | 2026-03-22 | reported | 2026-07-17 | superseded |
| source.project_id | 26063 | reported | 2026-07-17 | live |
| contact.email | Lesley.Wong@sfdpw.org | reported | 2026-07-17 | live |
| contact.name | Lesley Wong | reported | 2026-07-17 | live |
| agency.owner | SF DPW IDC - Hydraulic | reported | 2026-07-17 | live |
| project_type | Sanitary Sewer | reported | 2026-07-17 | live |
| phase | Design | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | 2350i | reported | 2026-07-17 | live |
| name | PW Various Locations Sewer Replacement (JV VL PR No 78) | reported | 2026-07-17 | live |