Major Transit Corridor Improvements — Transportation and Road Improvement GO Bond (2014)

funding source 0858f56e-7b01-4816-a374-88de852b9be5

This funding source is a component of San Francisco's 2014 Transportation and Road Improvement general obligation bond, approved by voters in November 2014, that pays for Major Transit Corridor Improvements. About $27.1 million was authorized, all of which has been issued, and roughly 99% has been spent, leaving about $470,000 remaining. Originally slated to finish at the end of 2022, the work is now projected to wrap up at the end of 2026, about four years behind its original schedule.AI-generated

Current record

FieldValueProvenance
funding.authorized $27,088,937 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“bondauthamount: 27088937 (fiscal_year FY24-25)”
funding.encumbered $0 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“encumbrance: 0 (fiscal_year FY24-25)”
funding.expended $26,716,341 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“expended: 26716340.594 (fiscal_year FY24-25)”
funding.issued $27,185,931 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“issuedtodate: 27185931 (fiscal_year FY24-25)”
funding.measure_year 2014 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“year: 2014”
funding.program Transportation and Road Improvement reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“bondprogram: Transportation and Road Improvement”
funding.remaining $469,590 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“remaining_balance: 469590 (fiscal_year FY24-25)”
funding.revised_budget $27,185,931 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“revisedbudget: 27185931 (fiscal_year FY24-25)”
funding.voter_approved 2014-11-04 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“voter_approved_date: 2014-11-04T00:00:00.000”
name Major Transit Corridor Improvements — Transportation and Road Improvement GO Bond (2014) derived socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“bondprogram: Transportation and Road Improvement; year: 2014; component_programitem: Major Transit Corridor Improvements”
schedule.end_original 2022-12-31 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“originalenddate: 2022-12-31T00:00:00.000”
schedule.end_projected 2026-12-31 reported socrata:m793-kis4 · retrieved 2026-07-29 · effective 2026-04-24
“projectedenddate: 2026-12-31T00:00:00.000”
summary This funding source is a component of San Francisco's 2014 Transportation and Road Improvement general obligation... generated llm:summarize · retrieved 2026-07-29
“generated from 12 resolved fields; input sha256-v2=44414fca38e43022773f3049389def994c97b7bd48fb6a729b2fb323dd40358e”

Source records

General Obligation Bond program spending and status key 2014|Transportation and Road Improvement|Major Transit Corridor Improvements primary · rule:gobonds-group-by-program-year-component dataset page ↗ · this record’s data ↗

Assertion history (latest 100, including superseded)

PredicateValueClassRecordedState
summary This funding source is a component of San Francisco's 2014 Transportation and Road Improvement general obligation bond, approved by voters in November 2014, that pays for Major Transit Corridor Improvements. About $27.1 million was authorized, all of which has been issued, and roughly 99% has been spent, leaving about $470,000 remaining. Originally slated to finish at the end of 2022, the work is now projected to wrap up at the end of 2026, about four years behind its original schedule. generated 2026-07-29 live
funding.voter_approved 2014-11-04 reported 2026-07-29 live
schedule.end_projected 2026-12-31 reported 2026-07-29 live
schedule.end_original 2022-12-31 reported 2026-07-29 live
funding.remaining $469,590 reported 2026-07-29 live
funding.encumbered $0 reported 2026-07-29 live
funding.expended $26,716,341 reported 2026-07-29 live
funding.issued $27,185,931 reported 2026-07-29 live
funding.revised_budget $27,185,931 reported 2026-07-29 live
funding.authorized $27,088,937 reported 2026-07-29 live
funding.measure_year 2014 reported 2026-07-29 live
funding.program Transportation and Road Improvement reported 2026-07-29 live
name Major Transit Corridor Improvements — Transportation and Road Improvement GO Bond (2014) derived 2026-07-29 live