Pier 80 Electrification
candidate project
Planning
079d9a06-c965-42cb-afdf-175d59d6b800
The Pier 80 Electrification project is a planning-phase effort led by the SF Port to install a 12kV electrical line underground running from the PG&E substation at 496 23rd Street to Pier 80, along parts of Cesar Chavez Street, Illinois Street, and 23rd Street. The work is currently active and scheduled to run from January 2025 through January 2028. No cost figures have been published.AI-generated
Current record
| Field | Value | Provenance |
|---|---|---|
| agency.owner | SF Port |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF Port” |
| contact.email | noel.aquino@sfport.com |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: noel.aquino@sfport.com” |
| contact.name | Noel Aquino |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Noel Aquino” |
| description | 12KV Electrical Line Underground Installation from PG&E substation at 496 23rd Street to CESAR CHAVEZ ST & ILLINOIS ST, CESAR CHAVEZ ST & ILLINOIS ST to 23RD ST & ILLINOIS ST, and ILLINOIS ST & CESAR CHAVEZ ST to MARYLAND ST & CESAR CHAVEZ ST |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“description: 12KV Electrical Line Underground Installation from PG&E substation at 496 23rd Street to CESAR CHAVEZ ST & ILLINOIS ST, CESAR CHAVEZ ST &...” |
| location.geometry | 3 geometries |
reported
socrata:btxj-k9uh · retrieved 2026-08-27
“3 published segment geometries” |
| location.street_limits | 23RD ST; CESAR CHAVEZ ST from MARYLAND ST to ILLINOIS ST; ILLINOIS ST from CESAR CHAVEZ ST to 23RD ST |
derived
socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields” |
| name | Pier 80 Electrification |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“name: Pier 80 Electrification” |
| phase | Planning |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Planning” |
| project_type | Roadway |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway” |
| schedule.end | 2028-01-28 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2028-01-28T00:00:00.000” |
| schedule.start | 2025-01-16 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2025-01-16T00:00:00.000” |
| source.project_id | 35655 |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 35655” |
| status | Active |
reported
socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active” |
| summary | The Pier 80 Electrification project is a planning-phase effort led by the SF Port to install a 12kV electrical line... |
generated
llm:summarize · retrieved 2026-07-18
“generated from 13 resolved fields; input sha256-v2=44d8d71aac274bb7f2f3e7e111d358f7a5d00646df5015fec7723d60ce30de89” |
Changes
| 2026-08-27 | field changed immaterial |
Source records
| Public Works coordinated projects (DotMaps) | key 35655 | primary · rule:dotmaps-group-by-dotmapsid | dataset page ↗ · this record’s data ↗ |
Assertion history (latest 100, including superseded)
| Predicate | Value | Class | Recorded | State |
|---|---|---|---|---|
| location.geometry | 3 geometries | reported | 2026-08-27 | live |
| summary | The Pier 80 Electrification project is a planning-phase effort led by the SF Port to install a 12kV electrical line underground running from the PG&E substation at 496 23rd Street to Pier 80, along parts of Cesar Chavez Street, Illinois Street, and 23rd Street. The work is currently active and scheduled to run from January 2025 through January 2028. No cost figures have been published. | generated | 2026-07-18 | live |
| location.geometry | 3 geometries | reported | 2026-07-17 | superseded |
| location.street_limits | 23RD ST; CESAR CHAVEZ ST from MARYLAND ST to ILLINOIS ST; ILLINOIS ST from CESAR CHAVEZ ST to 23RD ST | derived | 2026-07-17 | live |
| schedule.end | 2028-01-28 | reported | 2026-07-17 | live |
| schedule.start | 2025-01-16 | reported | 2026-07-17 | live |
| source.project_id | 35655 | reported | 2026-07-17 | live |
| contact.email | noel.aquino@sfport.com | reported | 2026-07-17 | live |
| contact.name | Noel Aquino | reported | 2026-07-17 | live |
| agency.owner | SF Port | reported | 2026-07-17 | live |
| project_type | Roadway | reported | 2026-07-17 | live |
| phase | Planning | reported | 2026-07-17 | live |
| status | Active | reported | 2026-07-17 | live |
| description | 12KV Electrical Line Underground Installation from PG&E substation at 496 23rd Street to CESAR CHAVEZ ST & ILLINOIS ST, CESAR CHAVEZ ST & ILLINOIS ST to 23RD ST & ILLINOIS ST, and ILLINOIS ST & CESAR CHAVEZ ST to MARYLAND ST & CESAR CHAVEZ ST | reported | 2026-07-17 | live |
| name | Pier 80 Electrification | reported | 2026-07-17 | live |