sfproj. every fact links to its evidence

← all projects

I-280 Southbound Ocean Avenue Off-Ramp Project

candidate project Design 030a8785-9f20-4a12-a853-149adba4b361

Current record

FieldValueProvenance
agency.owner SF CTA - County Transportation Authority reported socrata:btxj-k9uh · retrieved 2026-07-17
“agency_name: SF CTA - County Transportation Authority”
contact.email mike.tan@sfcta.org reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_email: mike.tan@sfcta.org”
contact.name Mike Tan reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_manager_name: Mike Tan”
description The project will realign the existing I-280 southbound off-ramp from a free-flow right turn roadway into a T-intersection for safety purposes. The project will also install traffic signals, curb ramps, and a bike lane. reported socrata:btxj-k9uh · retrieved 2026-07-17
“description: The project will realign the existing I-280 southbound off-ramp from a free-flow right turn roadway into a T-intersection for safety purposes. ...”
location.geometry 2 geometries reported socrata:btxj-k9uh · retrieved 2026-07-17
“2 published segment geometries”
location.street_limits I-280 S OFF RAMP from OCEAN AVE to I-280 S OFF RAMP; OCEAN AVE from GENEVA AVE to I-280 N ON RAMP derived socrata:btxj-k9uh · retrieved 2026-07-17
“assembled from segment on/from/to street fields”
name I-280 Southbound Ocean Avenue Off-Ramp Project reported socrata:btxj-k9uh · retrieved 2026-07-17
“name: I-280 Southbound Ocean Avenue Off-Ramp Project”
phase Design reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_phase: Design”
project_type Roadway reported socrata:btxj-k9uh · retrieved 2026-07-17
“facility_type: Roadway”
schedule.end 2028-12-31 reported socrata:btxj-k9uh · retrieved 2026-07-17
“end_date: 2028-12-31T00:00:00.000”
schedule.start 2023-07-01 reported socrata:btxj-k9uh · retrieved 2026-07-17
“start_date: 2023-07-01T00:00:00.000”
source.project_id 33655 reported socrata:btxj-k9uh · retrieved 2026-07-17
“dotmapsid: 33655”
status Active reported socrata:btxj-k9uh · retrieved 2026-07-17
“project_status: Active”

Source records

Public Works coordinated projects (DotMaps) key 33655 primary · rule:dotmaps-group-by-dotmapsid dataset page ↗ · this record’s data ↗

Assertion history (latest 100, including superseded)

PredicateValueClassRecordedState
location.geometry 2 geometries reported 2026-07-17 live
location.street_limits I-280 S OFF RAMP from OCEAN AVE to I-280 S OFF RAMP; OCEAN AVE from GENEVA AVE to I-280 N ON RAMP derived 2026-07-17 live
schedule.end 2028-12-31 reported 2026-07-17 live
schedule.start 2023-07-01 reported 2026-07-17 live
source.project_id 33655 reported 2026-07-17 live
contact.email mike.tan@sfcta.org reported 2026-07-17 live
contact.name Mike Tan reported 2026-07-17 live
agency.owner SF CTA - County Transportation Authority reported 2026-07-17 live
project_type Roadway reported 2026-07-17 live
phase Design reported 2026-07-17 live
status Active reported 2026-07-17 live
description The project will realign the existing I-280 southbound off-ramp from a free-flow right turn roadway into a T-intersection for safety purposes. The project will also install traffic signals, curb ramps, and a bike lane. reported 2026-07-17 live
name I-280 Southbound Ocean Avenue Off-Ramp Project reported 2026-07-17 live